Progress Status of TEPCO’s Roadmap towards Restoration from the Accident at Fukushima Daiichi Nuclear Power Station

Blog Post: Progress Status of TEPCO’s Roadmap towards Restoration from the Accident at Fukushima Daiichi Nuclear Power Station

TEPCO has released the following roadmap progress update on their effort to bring the situation at the Fukushima Daiichi Nuclear Power Station under control.
Progress status is given in the following areas:
  • Reactor(s) Cooling
  • Spent Fuel Pool(s) Cooling
  • Mitigation (Accumulated Water)
  • Mitigation (Groundwater)
  • Mitigation (Atmosphere/soil)

(click each picture to show the corresponding file)
Fukushima Roadmap Update

Fukushima Roadmap Update

Fukushima Roadmap Update