Southern seeks key NRC ruling to proceed with Ga. reactor project
Southern seeks key NRC ruling to proceed with Ga. reactor projectSouthern
Nuclear is seeking a "no objection" finding from the Nuclear Regulatory
Commission that would allow the Plant Vogtle expansion project in
Georgia to proceed while the agency studies a formal license-amendment
request concerning concrete. The amendment involves raising the
variability in the levelness of the concrete basemat of the site from 1
inch to 4 inches, and it would allow the use of additional concrete when
the basemat is poured. The Augusta Chronicle (Ga.)