Friday, August 3, 2012

Westinghouse, Shaw sue over additional nuclear construction costs

Plant Vogtle's contractors sue Georgia Power, project's co-owners

Atlanta Journal Constitution - ‎8 hours ago‎
In this Feb. 15, 2012 file photo, cooling towers for units 1 and. David Goldman, AP In this Feb. 15, 2012 file photo, cooling towers for units 1 and 2 are seen at left as the new reactor vessel bottom head for unit 3 stands under construction at right at the Vogtle ...

Article fails to tackle nuclear plants' other issues

The Reporter -
Article fails to tackle nuclear plants' other issues. Posted: 08/02/12 08:39 pm. Having been employed for more than 40 years in a segment of the electric power industry, I have concerns that (Ray Henry's) article, which was published in several newspapers, ...

Plant Vogtle contractors sue Georgia Power, project partners

Upstart -
Enlarge Image. Georgia Power's Atlanta HQ. Dave Williams: Staff Writer- Atlanta Business Chronicle. Two of the contractors building two additional nuclear reactors at Georgia Power Co.'s Plant Vogtle are suing the Atlanta-based utility in federal court.

Vogtle is Latin for Cost Overruns

Peach Pundit -
Kristi “Kickass” Swartz of the AJC reports that Georgia Power has been sued in Federal Court by Westinghouse (the reactor maker) and Shaw for allegedly materially misrepresenting the amount of soil available for backfill. Backfill is important to gaining ...

Westinghouse, Shaw sue over additional nuclear construction costs

Power Engineering Magazine -
Westinghouse and a subsidiary of The Shaw Group (NYSE: SHAW) are suing Georgia Power, a unit of Southern Co. (NYSE: SO), and co-owners of the Vogtle nuclear power plant for breach of contract due to additional construction expenses, according to ...

No comments:

Post a Comment