Friday, November 14, 2014

Tianwan 3 Completes Internal Construction

Tianwan 3 Completes Internal Construction

Chief Executive Officer at Dynatom International GmbH 


Construction of the reactor building at the third unit of the Tianwan nuclear power plant under construction is nearing completion. The final concrete for the reactor building's walls was poured on 11 November, China National Nuclear Corporation (CNNC) announced. The containment building now stands 38 meters tall and has a radius of 21.8 meters.

The next stage in the unit's construction will be the installation of the dome on top of its containment building.

Source: http://np.chinapower.com.cn/201411/13/0042851.html