EM News Flash | March 3, 2017 |
Crews at the DOE Idaho Site Complete Transuranic Waste Retrieval
EM's Acting Assistant Secretary Sue Cange and Idaho's Governor C.L. "Butch" Otter speak to a crowd in celebration of the completion of the retrieval of
over 53,000 cubic meters of waste at the Advanced Mixed Waste Treatment Project.
Idaho Falls, Idaho - For more than 20 years, a gigantic building – covering seven acres of land at the U.S. Department of Energy’s Idaho
site – has been the temporary storage location for hundreds of
thousands of containers filled with radioactively contaminated
materials.
About the size of an aircraft carrier, the Transuranic Storage
Area-Retrieval Enclosure (TSA-RE) covered an earthen berm that protected
more than 50,000 cubic meters of metal drums and boxes containing
transuranic waste. In February, the final box was safely retrieved
bringing an end to retrieval activities at the Department’s Advanced
Mixed Waste Treatment Project, located 50 miles west of Idaho Falls, ID.
An additional 15,000 cubic meters of waste had been stored in nearby
storage modules and is included in the project.
Retrieval of the above-ground stored transuranic waste was scheduled
to be completed by this May. But an experienced workforce, innovative
tools, and a safe work mindset enabled the project to finish ahead of
schedule.
“Completing the retrieval of the waste stored in TSA-RE is an
important achievement for the Department of Energy,” said Jack
Zimmerman, Deputy Manager for the Idaho Cleanup Project at the DOE Idaho
Operations Office. “Retrieving waste that has been buried in an earthen
berm for nearly 40 years is a complicated task, and to complete the
work safely and ahead of schedule is a testament to the experience and
tenacity of this project’s employees.”
When excavation and retrieval activities started in 2003, backhoes and
shovels were used to remove dirt from the 35-foot tall earthen berm to
start retrieving drums and boxes. The first containers retrieved, having
been under the berm the least amount of time, were in good structural
shape and could be safely removed and stored, prior to their
characterization, treatment, and shipment out of Idaho. However, as the
project progressed to the older containers, the condition of the
containers was noticeably degraded.
“The complexity and hazards that retrieval crews faced while
performing their work cannot be overstated. Many of the final drums and
boxes were degraded after decades under dirt, challenging our workers,”
said Fred Hughes, Program Manager for Idaho Cleanup Project contractor
Fluor Idaho. “Understanding what they were up against, these skilled
crews, working with robust administrative and engineered controls, made
remarkable progress in further protecting the Snake River Plain
Aquifer.” Fluor Idaho oversees environmental management work for the
Department of Energy at its Idaho site.
During
the final five years of retrieval, crews reached containers that had
been under the dirt for decades; many degraded containers were
encountered. Through a thoughtful, deliberate approach, specially
developed tools, and a confidence borne from experience crews were able
to remove the degraded containers, repack the materials into new sturdy
containers, and complete retrieval of the waste without any unexpected
release of contamination, serious injury, or incident.
Each of the drums and boxes retrieved from the TSA-RE has, or will be,
repackaged and prepared for shipment out of Idaho for final disposal in
accordance with the 1995 Idaho Settlement Agreement.
|
No comments:
Post a Comment