Charting the International Roadmap to a Demonstration Fusion Power Plant
More than 60 top fusion scientists and engineers from around the world gathered at the 5th IAEA DEMO Programme Workshop
in Daejeon, South Korea, from 7 to 10 May, to discuss critical issues
and next steps on the road to the realization of fusion energy.
While science and technology issues for fusion power are broadly agreed upon, upscaling the technology to commercial electricity generation is still decades away. This workshop aimed to help experts define the facilities and activities that can lead to the resolution of some of the key scientific and technological challenges to developing a fusion demonstration power plant (DEMO).
Such DEMO would show that controlled nuclear fusion can generate net electrical power and mark the final step before the construction of a commercial fusion power plant. This would represent the next stage after ITER, the world’s largest fusion experiment under way, which is expected to demonstrate by the late 2030s that fusion can be used to generate net energy, i.e. produce more energy than supplied to it to feed the reactor. Crucially, however, energy produced by ITER will not be transmitted to the electricity grid.
While science and technology issues for fusion power are broadly agreed upon, upscaling the technology to commercial electricity generation is still decades away. This workshop aimed to help experts define the facilities and activities that can lead to the resolution of some of the key scientific and technological challenges to developing a fusion demonstration power plant (DEMO).
Such DEMO would show that controlled nuclear fusion can generate net electrical power and mark the final step before the construction of a commercial fusion power plant. This would represent the next stage after ITER, the world’s largest fusion experiment under way, which is expected to demonstrate by the late 2030s that fusion can be used to generate net energy, i.e. produce more energy than supplied to it to feed the reactor. Crucially, however, energy produced by ITER will not be transmitted to the electricity grid.
Dealing with the heat
Fusion energy
has existed for billions of years in the Sun, but its reproduction on
Earth in a controlled and durable manner remains a challenge. Unlike
fission, where atoms are split to produce energy, in fusion two lighter
nuclei are joined together to make a heavier nucleus, while energy is
released. In a controlled nuclear fusion power plant, three conditions
must be fulfilled:
- very high temperature (more than 10 times hotter than the centre of the Sun) to provoke highly energetic collisions at extreme speed,
- sufficient particle density in the plasma – where the reaction takes place – to increase the probability of collisions, and
- sufficient confinement to hold the plasma and allow the fusion reactions to take place continuously.
Building on ITER
The missing
piece to producing net power remains better confinement, which is a
measure of how good the magnetic field is at keeping the plasma energy,
for which a bigger tokamak, such as ITER is needed. Afterwards, the
technological challenges of bringing fusion power to the electricity
grid will be addressed by a DEMO-type
reactor. Individual countries are exploring ways to do this, and the
IAEA is providing a platform for information sharing and exchange in
order to facilitate the research and technology development.
China has made significant progress in planning for a device called China Fusion Engineering Test Reactor (CFETR) that would bridge the gaps between ITER and DEMO. Construction of the CFETR could start at around 2020 and be followed by construction of a DEMO in the 2030s.
The European Union and Japan are jointly building a powerful tokamak called JT-60SA in Naka, Japan, as a complement to ITER on a privileged partnership called the Broader Approach Activities. In addition to constructing the JT-60SA, the joint programme consists of two other projects, the Engineering Validation and Engineering Design Activities for the International Fusion Materials Irradiation Facility (IFMIF/EVEDA), and the International Fusion Energy Research Centre (IFERC). This partnership represents a well-integrated approach to support ITER and to prepare to undertake the engineering design and construction of a subsequent DEMO.
India has announced plans to begin building a device called SST-2 to develop components for a DEMO around 2027, and then start construction of a DEMO in 2037.
South Korea initiated a conceptual design study for a K-DEMO in 2012 targeting the construction by 2037 with potential for electricity generation starting in 2050. In its first phase (2037-2050), K-DEMO will develop and test components and then utilize these components in the second phase after 2050 to demonstrate net electricity generation.
Russia plans the development of a fusion-fission hybrid facility called DEMO fusion neutron source (FNS), a reactor that would harvest the fusion-produced neutrons to turn uranium into nuclear fuel and destroy radioactive waste. The DEMO-FNS is planned to be built by 2023, and is part of Russias’ fast-track strategy to a fusion power plant by 2050.
The United States of America is considering an intermediate step called Fusion Nuclear Science Facility (FNSF) to be used for the development and testing of fusion materials and components for a DEMO-type reactor. Plans call for operation to start after 2030, and construction of a DEMO after 2050.
Main findings and discussion carried out in the IAEA DEMO Programme Workshop series can be found here.
China has made significant progress in planning for a device called China Fusion Engineering Test Reactor (CFETR) that would bridge the gaps between ITER and DEMO. Construction of the CFETR could start at around 2020 and be followed by construction of a DEMO in the 2030s.
The European Union and Japan are jointly building a powerful tokamak called JT-60SA in Naka, Japan, as a complement to ITER on a privileged partnership called the Broader Approach Activities. In addition to constructing the JT-60SA, the joint programme consists of two other projects, the Engineering Validation and Engineering Design Activities for the International Fusion Materials Irradiation Facility (IFMIF/EVEDA), and the International Fusion Energy Research Centre (IFERC). This partnership represents a well-integrated approach to support ITER and to prepare to undertake the engineering design and construction of a subsequent DEMO.
India has announced plans to begin building a device called SST-2 to develop components for a DEMO around 2027, and then start construction of a DEMO in 2037.
South Korea initiated a conceptual design study for a K-DEMO in 2012 targeting the construction by 2037 with potential for electricity generation starting in 2050. In its first phase (2037-2050), K-DEMO will develop and test components and then utilize these components in the second phase after 2050 to demonstrate net electricity generation.
Russia plans the development of a fusion-fission hybrid facility called DEMO fusion neutron source (FNS), a reactor that would harvest the fusion-produced neutrons to turn uranium into nuclear fuel and destroy radioactive waste. The DEMO-FNS is planned to be built by 2023, and is part of Russias’ fast-track strategy to a fusion power plant by 2050.
The United States of America is considering an intermediate step called Fusion Nuclear Science Facility (FNSF) to be used for the development and testing of fusion materials and components for a DEMO-type reactor. Plans call for operation to start after 2030, and construction of a DEMO after 2050.
Main findings and discussion carried out in the IAEA DEMO Programme Workshop series can be found here.