Thursday, December 19, 2019

System tests further delay Finnish EPR start-up - World Nuclear News

System tests further delay Finnish EPR start-up - World Nuclear News: The loading of fuel into the core of the Olkiluoto 3 has been delayed until June next year because of the slow progress of system tests and shortcomings in spare part deliveries, the Areva-Siemens consortium has informed Finnish utility Teollisuuden Voima Oyj. Grid connection of the EPR is now scheduled for November, with the start of regular electricity production expected in March 2021.

No comments:

Post a Comment