Counting the Steps to a Final Watts Bar Unit 2 Decision

06/01/2015 08:58 AM EDT

Jeanne Dion Project Manager Office of Nuclear Reactor Regulation The NRC’s Commissioners have given the staff the authority to issue the Tennessee Valley Authority (TVA) a full-power operating license for Unit 2 at the Watts Bar nuclear power plant site in Tennessee. That permission has some strings attached, however, so we’re still months away from […]http://public-blog.nrc-gateway.gov/2015/06/01/counting-the-steps-to-a-final-watts-bar-unit-2-decision/?source=govdelivery&utm_medium=email&utm_source=govdelivery
 
 
Jeanne Dion
Project Manager
Office of Nuclear Reactor Regulation

The NRC’s Commissioners have given the staff the authority to issue the Tennessee Valley Authority (TVA) a full-power operating license for Unit 2 at the Watts Bar nuclear power plant site in Tennessee. That permission has some strings attached, however, so we’re still months away from our final licensing decision.
wattsbarconstructionsriIf TVA is issued the license, Watts Bar 2 will be the first U.S. nuclear power plant to start operating since 1996, when Watts Bar 1 came online. TVA still has to satisfy the staff that several regulatory requirements for safe operation of Unit 2 have been met. We’re finishing up the licensing and inspection activities we need to conclude TVA is ready to load fuel and operate the reactor, which is near Spring City, Tenn.
We have to be satisfied not only that Unit 2 is safe to operate, but also that TVA can safely transition to operating two reactors at the site. We’re completing a few licensing actions needed to support dual-unit operation at Watts Bar. TVA also has to pass our remaining operational readiness inspections.
Other upcoming milestones include getting a recommendation from the NRC’s Region II Administrator, who has oversight responsibility for all inspections performed at Watts Bar 2. We also need to issue a couple supplements to the reactor’s Safety Evaluation Report.
TVA’s progress in completing construction and testing of Watts Bar 2 will directly influence our completion of the milestones. We may be able to make a licensing decision later this year. TVA has said repeatedly, however, that the actual operating license date depends on several factors and could shift as the final months’ work is completed. While we take TVA’s schedule into consideration for planning our licensing and inspection work, our priority is always on ensuring safety.
If we conclude Unit 2 is safe and ready to receive a license, TVA will still have to successfully complete several tests, including running the reactor at gradually increasing power levels, before the reactor can provide electricity to the grid. The NRC website has more information on the past few years of Watts Bar Unit 2’s licensing and inspection activities.