Counting the Costs on Advanced Reactor Reviews
October 29, 2015
Posted by on Advanced Reactors and Policy Branch
Office of New Reactors
We’re continuing to examine topics from the recent two-day public workshop we jointly hosted with the Department of Energy regarding non-light water reactor designs. One topic getting a lot of attention is the possible costs for NRC reviews of applications for these designs.
For instance, some people interpreted a DOE presentation on the Next Generation Nuclear Plant project as saying it costs $800 million to receive a final certification or license from the NRC. The bulk of that $800 million, however, falls outside of NRC fees and would be made up of the designer’s costs to develop and test its design to ensure that it works as planned.
In other words, the designer does not pay the NRC $800 million to review a reactor design. Looking at recent reviews of large light-water reactors, we see designers spent approximately $50 – $75 million for NRC fees to certify their designs.
A recent Government Accountability Office assessment, “Nuclear Reactors: Status and Challenges in Development and Deployment of New Commercial Concepts” says costs can be “…up to $1 billion to $2 billion, to design and certify or license the reactor design.” A different portion of the GAO report, however, pointed out most of these costs aren’t attributable to the NRC review. The largest part of the price tag would be research, development, and design work to develop and test a new reactor design.
We can also examine information from the public workshop on design development costs versus NRC review costs for the developer of a new small modular reactor design. The company said that of approximately $300 million in design investment to date, only $4 million of that amount (or slightly more than 1 percent) is from NRC fees for several years of pre-application interactions with the agency.
Here’s something to keep in mind: NRC review costs depend on the quality and maturity of the applicant’s information. The NRC always aims to efficiently and effectively review designs. Incomplete or inadequate information will very likely increase costs, however, since the NRC will spend more time and effort getting the data necessary to determine whether the reactor could operate safely and securely.
Everyone benefits from a common understanding of NRC costs as we discuss the next generation of reactor designs. The NRC’s website has more information on how the agency is approaching advanced and small modular reactor designs.