Michele Kearney's Nuclear Wire

Major Energy and Environmental News and Commentary affecting the Nuclear Industry.

Wednesday, February 8, 2012

Update from I-Nuclear 10 years, €2.8 billion later, decommissioning a distant goal in Bulgaria, Lithuania, Slovakia by I-Nuclear

New post on i-NUCLEAR

10 years, €2.8 billion later, decommissioning a distant goal in Bulgaria, Lithuania, Slovakia

by I-Nuclear
Ten years after the European Union began providing €2.8 billion of financial assistance to Bulgaria, Lithuania and Slovakia for the closure of ‘unsafe’ Soviet-era reactors, decommissioning of those reactors remains a distant goal, according to a new report.
In a special report released February 8, the European Court of Auditors (ECA) said that the reactors have all been shut down and partly defuelled, major preparatory works have been implemented and dismantling works have started.
“However, after more than 10 years of EU assistance, progress has been slow, as many projects still involve preparatory activities. Moreover, the situation is rather unclear concerning the needs still to be met as a result of the early closure since no comprehensive needs assessment exists,” the report said.
The main work “is still ahead and its finalisation faces a significant funding shortfall” of around €2.5 billion, the auditors said.
The identification of decommissioning activities is still in progress, the ECA report said. “Major infrastructure projects face delays and cost-overruns. Cost estimates are not complete in the absence of key information on radioactive waste and/or the facilities and technologies required for their treatment,” the report said.
The auditors found that a broad variety of activities were funded to mitigate the consequences on the countries’ energy supply of the nuclear reactors’ early closure, “but the degree of mitigation achieved is not known.”
The auditors said that should the European Commission follow through with plans to provide additional financial assistance after 2013 when the current program ends, the support “should be made conditional upon an ex ante evaluation of the EU added value of such intervention, identifying the specific activities to be financed through the EU budget and taking account of other funding facilities such as Structural Funds.”

 Reactors closed 2002-09

The EU assistance provided for the closure of the reactors came as part of the negotiations between the three countries over their entry into the European Union, known as accession.
Under their respective accession agreements, Bulgaria agreed to close the four VVER 440 reactors at Kozloduy, Lithuania agreed to close the two RBMK reactors at Ignalina, and Slovakia agreed to close the two VVER 440s at Bohunice V1.
The EU committed some €2.8 billion between 1999 and 2013 for the three countries, according to the report, both to assist in reactor closures and to providing alternative energy projects to compensate for the loss of productive reactors.
As of December 31, 2010, when the auditors completed their review, the Commission had committed over 70% of the EU financial contribution or €2.06 billion.
Payments to contractors stood at €1.03 billion, representing almost half of com- mitted amounts, the report said.
Out of this amount, some 60 % and 40%, respectively, went to decommissioning and mitigation measures, the auditors said.
In March 2011 the recipient countries updated their decommissioning cost estimates, to reach €5.3 billion, the report said.  A comparison with the decommissioning funding currently available at national and programme level suggests a shortfall of around €2.5 billion, the auditors said.
Slovakia has committed itself to topping up the funding needed for decommissioning and has created a specific funding mechanism (a tax on electricity transmission) to contribute towards reducing the funding shortfall, the report said.
Lithuania and Bulgaria have not put in place any equivalent mechanism. The absence of sufficient funding arrangements puts the completion of the decommissioning processes at risk, it said.
In Bulgaria, an experimental plasma melting technology was selected in Kozloduy without proper demonstration of its effectiveness and without due consideration of the design and construction costs (some €30 million compared to one fifth that for traditional technologies), the report said.
In Lithuania, at the time of the audit visit, the major infrastructure projects, which are a precondition for the decommissioning of the Ignalina Nuclear Power Plant, were significantly delayed compared with initial contract completion dates.
The delays included: the interim spent fuel facility — more than 32 months; the solid waste retrieval facility — 44 months; the solid waste treatment and storage facility for the management of short- and long-lived low and intermediate level radioactive waste — 34 months. The total project cost of the interim spent fuel facility increased by €22 million (15.6 %), the auditors said.
In Slovakia, the interim radioactive waste storage at the Bohunice site, initially expected to be commissioned in 2010, was still in procurement process during the audit.
As a result, the availability of buffer storage areas has been identified as a potential bottleneck. The facility for the free release of decommissioning materials was delayed by more than one year. Until the facility is operational, no material can be released from Bohunice V1 NPP, the report said.

Commission Responds

The European Commission was allowed to view and respond to the report before it was made public February 8. Its response was included in the report.
The Commission defended the program, saying that “without the EU funds provided for decommissioning and mitigation,” the reactors would not have been shut down, “particularly given the concerted political pressure in these three Member States, which reached its peak during the severe gas supply crisis in early 2009.”
The Commission said the financial assistance provided was an expression of “solidarity” with the new member states and was never intended to provide a set portion of the total decommissioning costs.
The Commission said that “delays and cost overruns are not unusual,” given that projects financed by the programmes are often long, complex and politically sensitive.
The Commission said that the “ultimate responsibility for decommissioning and its financing” is on the nation state, and it is not the EU’s responsibility to make up any shortfall.
Nonetheless, the Commission said, plans for additional financial assistance for the period 2014-20 are under discussion, but such support would be conditional on the three countries “committing adequate additional resources.” –David Stellfox
I-Nuclear | February 8, 2012 at 5:50 pm | Categories: Decommissioning, EU | URL: http://wp.me/p22dAl-8a

No comments:

Post a Comment