EM Update | Vol. 8, Issue 19 | Oct. 17, 2016
|
|||||
|
|||||
EM’s Mark Whitney Reflects on DOE Tenure
How would you compare EM today to when you came to headquarters?
What are the main things you’re most proud of during your tenure in EM?
What do you think will be EM’s next major near-term accomplishment?
Now, is there something you wish you could go back and do over or do differently?
What words of advice would you give to your successor?
What can you tell us about your future plans? What are you most looking forward to?
Twenty Years of Preparations to Culminate in Plutonium Finishing Plant Demolition
Demolition
will progress from the Plutonium Reclamation Facility (green) to the
Americium Recovery Room (red) during the remainder of 2016. Demolition
of the main processing facility (blue) and the fan house and ventilation
stack (orange) will begin in spring 2017.
RICHLAND, Wash. – Demolition of the Hanford Site’s Plutonium Finishing Plant (PFP) is scheduled to begin within weeks, capping years of challenging preparatory work.
EM’s Richland Operations Office
and contractor CH2M HILL Plateau Remediation Company (CH2M) will
conduct demolition slowly and methodically, with numerous controls and
extensive monitoring in place to ensure employee and environmental
safety.
“Today, we’re near the end of a 20-year remediation project to prepare
the facility for safe demolition,” EM Federal Project Director Tom
Teynor said. “The start of its demolition will represent a huge step
forward for the Department, plant workers, the community, and
stakeholders, as well as the agencies we’ve worked with to get to this
point.”
Crews open a portion of the PRF roof to remove pre-staged glove boxes inside.
Crews recently opened portions of the Plutonium Reclamation Facility
(PRF) roof for a crane to remove eight glove boxes from the upper three
floors (see a time lapse video here).
Crews had already cleaned, decontaminated and prepared the glove boxes
for removal. Heavy equipment will demolish PRF after those hazards are
removed.
“We will move forward through demolition with our continued focus on
safety and each other, our continued cooperation, our teamwork and our
skillful approach to every task,” said Tom Bratvold, CH2M’s vice
president of the PFP Closure Project. “If we aren’t sure we can do it
safely, we won’t do it.”
Glove boxes will be removed from PRF and packaged for off-site disposal.
PRF is the first of four main PFP facilities to be demolished. Next is the Americium Recovery Facility, nicknamed the “McCluskey Room”
after a 1976 explosion that severely injured Harold McCluskey, who was
working inside. Using personal protective equipment, CH2M employees have
already prepared that building for demolition.
Demolition of the main processing and ventilation facilities is
expected to begin in early 2017. Crews have prepared the main building,
which is the largest of the four, by removing (or prepared to remove
during demolition) about 75 percent of contaminated process vacuum
piping and 65 percent of the contaminated ventilation duct. Workers are
removing asbestos, contaminated piping and filter boxes from the
ventilation building.
All demolition is scheduled for completion in summer 2017.
West Valley Site Prepares for Vitrification Facility Demolition in 2017
Workers verify deactivation progress in the vitrification cell.
WEST VALLEY, N.Y. – EM’s West Valley Demonstration Project
has completed 95 percent of deactivation activities at the
Vitrification Facility, preparing for its scheduled demolition in spring
2017, several months ahead of schedule.
Workers safely and compliantly removed all major equipment, cleaned
and sealed interior surfaces, disconnected all utilities and connections
with adjoining structures and obtained characterization data to plan
for demolition and waste disposal.
Demolition will produce approximately 6,500 tons of material requiring
transport for disposal. EM and contractor CH2M HILL BWXT West Valley
will conduct the demolition under the protocols used for the teardown of
the site’s once-contaminated 01-14 Building in 2013.
A cutaway drawing shows the internal workings of the Vitrification Facility.
Operating from 1996 to 2002, the Vitrification Facility produced 275
stainless steel canisters from solidifying 600,000 gallons of liquid
high-level waste and sludge generated from spent nuclear fuel
reprocessing. The facility is made up of a vitrification cell, which
housed all major radioactive process equipment, operating aisles and
working areas, and auxiliary buildings.
Standing 50 feet tall with walls and a roof up to 4 feet thick, the
11,000-square-foot concrete Vitrification Facility is reinforced with
structural steel and sided with sheet steel. Demolition workers will use
heavy equipment to size-reduce the waste and load it into containers
before shipping it to an off-site licensed disposal facility.
All activities will be conducted in accordance with state, federal and
regulatory requirements. Workers placed 16 ambient air monitoring
stations at locations outside the site boundary and will install
real-time air monitors around the demolition area to monitor for
potential airborne contamination releases.
An
aerial view of the West Valley Demonstration Project. The Vitrification
Facility’s deactivation activities are 95 percent complete and the Main
Plant Process Building’s deactivation activities are 56 percent
complete.
WVDP took special precautions to protect the workers, public and
environment from radiological and hazardous constituents prior to
demolition and to ensure safe handling of building debris, including:
Proposal to Control Tank Vapors Wins ORP’s Grand Challenge
Mark
Edgren, ORP chief of staff, left, presents Larry Shaffer and Clinton
Summers with a plaque announcing their Grand Challenge-winning proposal.
The two were part of a four-person team whose proposal aims to destroy
organic bearing compounds and remove mercury by installing special
skid-mounted treatment units to the vent pipes of Hanford tanks.
RICHLAND, Wash. –
A proposal to destroy organic bearing compounds and remove mercury by
installing special skid-mounted treatment units to the vent pipes of
tanks in Hanford’s tank farms was recently named the winner of the 2016
Grand Challenge.
Participants in the annual competition, now in its fourth year, propose and present creative ideas that can make a significant difference in the safety, quality, schedule and cost of EM’s Office of River Protection (ORP) mission. Judges then evaluate and select ideas for potential implementation.
The target cost savings for each Grand Challenge proposal is over $250 million.
A four-member team made up of Joe Enneking, Larry Shaffer, Clinton
Summers and Paul Kovach of the Columbus, Ohio-based NUCON International,
Inc. won with their proposal titled “Control of Vapors from Hanford
Storage Tanks.”
Their proposal would require about $1 million to produce and test a
prototype, but could save ORP up to $20 million a year. That could mean
more than $250 million as tank farms activities are anticipated through
at least 2040.
Grand Challenge judges reviewed 34 submissions from 20 organizations
and partnerships, and selected 10 finalists who presented their
proposals in September. Judges looked at factors such as technical
viability and risks, whether proposals were achievable within a
timeframe to meet mission needs, whether they were executable with
existing safety basis requirements, cost avoidance, cost savings, and
process efficiencies.
ORP will study about 18 of the proposals for potential implementation,
according to Ricky Bang, an ORP facility representative and Grand
Challenge advisor.
If only the top 10 were implemented, it could save taxpayers a
significant amount of money, said Elaine Diaz, ORP’s chief engineer and
Grand Challenge lead advisor.
“Grand Challenge is about getting the job done better, safer and
sooner, and spending less of our tax dollars in the process. We all want
that,” she said. “By tapping into great ideas from industry, academia,
our network of national labs, and our own employees, we can make a
significant difference.”
Employees from DOE and its contractors, national laboratories, universities and corporations entered submissions.
“I think this year was good because a variety of organizations
participated,” said Bang. “I would say we got an improvement over last
year through the increased collaboration between organizations. That
resulted in better, more complete ideas that we can study.”
The second-place proposal was “Optimization of Sodium Concentration in
Direct-Feed, Low-Activity Waste Feed,” by Sahid Smith, Wendell
Wrzesinski and Ben Harp, all from ORP.
The third-place proposal was “Hanford Waste Storage Capacity
Management: Double-Shell Tank Life Extensions Supported by Forensics,
Diagnostics, and Prognostics,” by Kayte Denslow, Kenneth Johnson, and
Michael Rinker of the Pacific Northwest National Laboratory; Kayle
Boomer, Theodore Venetz and Jason Gunter of contractor Washington River
Protection Solutions; and Dennis Washenfelder of AEM Consulting.
EM Marks Groundwater Characterization Milestone at Nevada Site
NNSS
Scientist Jenny Chapman (foreground) discusses groundwater
characterization at Frenchman Flat with a resident of Amargosa Valley,
Nev. at the 2016 NNSS Groundwater Open House.
LAS VEGAS – EM recently achieved a groundwater characterization milestone at the Nevada National Security Site (NNSS) when
the State of Nevada Division of Environmental Protection approved
transitioning a groundwater investigation area to long-term monitoring.
That’s the end goal of a strategy outlined in the Federal Facility
Agreement and Consent Order for five groundwater investigation areas at
NNSS. Frenchman Flat, the site of 10 underground nuclear tests between
1965 and 1971, is the first to enter this important final stage.
The Frenchman Flat success follows over 20 years of hard work and
continuous study by multiple organizations, including two external peer
reviews. In that time, multiple groundwater characterization wells were
drilled, three-dimensional computer models were developed and refined
and boundaries for restricted access were established.
“The NNSS is one of the most studied locations in the world, and this
achievement is a testament to the teamwork between all organizations
involved,” said Bill Wilborn, manager of NNSS groundwater
characterization for EM.
The underground nuclear tests at Frenchman Flat provided valuable data
in a few spectacular seconds. In the decades to follow, NNSS scientists
worked to understand the effects of those tests on the site’s
groundwater. Their studies confirmed that the contamination from nuclear
testing in groundwater at Frenchman Flat poses no risk to the public.
While entering long-term monitoring signifies a thorough understanding
of the groundwater flow system, routine monitoring at Frenchman Flat
will continue, and results will continue to be reported annually in a publicly-released report.
Scientists prepared a report detailing
the Frenchman Flat studies. Their findings include that contaminated
groundwater is not expected to leave the Frenchman Flat basin, and that
radionuclides in the groundwater will travel less than a mile in 1,000
years.
“The groundwater flow system and potential for contaminant movement is
well understood, to the point that protection of the public is
ensured,” said Wilborn.
Transitioning Frenchman Flat to long-term monitoring provided NNSS
scientists and staff with an invaluable experience for understanding the
necessary balance of modeling, monitoring and restricted access
protective of the public and the environment. It also sets the stage for
other NNSS groundwater investigation areas.
“Although the regulatory strategy is the same, each will have unique
challenges due to the varying subsurface environments,” said Wilborn.
NNSS groundwater studies will continue with the goal of transitioning all areas of the NNSS to long-term monitoring.
Click here to learn more about groundwater characterization at the NNSS.
DOE Representatives Mark 60 Years of IAEA General Conference
EM
Assistant Secretary Monica Regalbuto (front row, second from right), at
a recent U.S.-hosted reception at the Palais Ferstel in Vienna
celebrating the 60th anniversary of the International Atomic Energy Agency’s
(IAEA) General Conference. Also pictured, front row, left to right, are
Ben McRae with the DOE Office of General Counsel, IAEA Director General
Yukiya Amano, and Farah Benahmed, NE; back row, left to right, Michelle
Scott, NE, NE Acting Assistant Secretary John Kotek, Andrew Richards,
NE, and Aleshia Duncan, Organization for Economic Cooperation and
Development Nuclear Energy Agency.
Paducah Site Improves Groundwater Treatment
Operators drill wells during the first phase of the project to further optimize groundwater treatment.
PADUCAH, Ky. – Nine new monitoring wells have been installed in the northeast section of EM’s Paducah Site, representing the first phase of a project to enhance groundwater treatment.
Data from the new wells will support the project’s next phase, which
includes installing an additional 13 monitoring wells, two extraction
wells, and a new treatment facility to augment the existing
pump-and-treat unit. The next phase begins when samples from the nine
new monitoring wells are assessed.
A horseshoe-shaped area of contaminated groundwater plumes containing
trichloroethene (TCE) extends under the site. TCE was used to clean
equipment when the gaseous diffusion plant operated. The chemical’s use
was discontinued in the early 1990s.
Two pump-and-treat operations reduced the size of the plumes’
high-concentration portion. More than 3.6 billion gallons of water were
treated and more than 4,200 gallons of contamination were removed from
the groundwater.
“The optimization project is another positive step in containing and
controlling the groundwater contamination at the Paducah Site,” said
Dave Dollins, project manager with EM’s Portsmouth/Paducah Project Office (PPPO).
Fluor Federal Services, as EM’s prime contractor for the Paducah Deactivation Project, is setting up the new systems.
“The first phase of installing the new monitoring wells is a major
undertaking and key to the successful outcome of the optimization,”
Fluor Paducah Deactivation Project Environmental Management Director
Myrna Redfield said.
Like EM on Facebook:Moab Project Hosts International Meeting on Uranium Mining and Remediation
The visitors pose for a group photo on the disposal cell cover at the Crescent Junction site.
GRAND JUNCTION, Colo. – More than 40 people from around the world met recently for the International Atomic Energy Agency (IAEA) meeting to share lessons learned and address environmental aspects of uranium mining and remediation projects.
EM’s Moab Uranium Mill Tailings Remedial Action Project hosted the meeting and provided a tour of EM’s project sites in Moab, Utah to the
environmental and project managers, operators, researchers and
regulators from the U.S. and 13 other countries in attendance.
The meeting at Colorado Mesa University in Grand Junction highlighted
the local academic institution, which offers degrees in environmental
science and geology and is expanding its engineering programs.
University President Tim Foster welcomed the group.
Dr. Peter Woods, IAEA’s organizer, considered the meeting a success.
“I have had very positive feedback from participants,” he said. “With
26 technical talks involving over 40 participants from 13 IAEA Member
States, the meeting was diverse and well attended. This shows the wide
interest in the topic of the remediation of former uranium mining and
milling sites.”
The participants toured the site where 16 million tons of mill
tailings, the remains from the former uranium-ore processing mill, are
being excavated, conditioned and placed in metal containers for shipment
by rail to Crescent Junction for permanent disposal.
EM
Federal Project Director Donald Metzler (orange vest) discusses mill
tailings removal and conditioning processes during the Moab Site tour.
EM Federal Project Director Donald Metzler and Moab Technical
Assistance Contractor Senior Program Manager Joe Ritchey described the
regional geology and history to the tour participants as they traveled
by bus 100 miles from Grand Junction to Moab.
Longtime Moab Mayor Dave Sakrison kicked off the tour in Moab,
emphasizing the importance of working with the local community to gain
support for cleanup projects.
Metzler, who gave an overview of the Moab project to the tour
participants, has a long history of participation in IAEA meetings,
especially with the Uranium Mining and Remediation Exchange Group, which
was adopted under the IAEA in 2012.
“Being the host for one of these meetings, which I feel benefits our
project as much as any of the others discussed, has been on my bucket
list for many years. I’m glad we were able to show other parts of the
world the important work that we’re doing to take care of our legacy
waste,” Metzler said.
Woods expressed his appreciation for the tour.
“The field trip to the Moab project, including the disposal cell site
at Crescent Junction, was a highlight for many,” Woods said. “I thank
the DOE team for their great cooperation, organization and hospitality.”
New Idaho Site Robotic Technology Adds Muscle, Enhances Safety
Waste awaiting retrieval at AMWTP’s Transuranic Storage Area Retrieval Enclosure.
IDAHO FALLS, Idaho – Thanks to new robotic gear, EM’s Idaho Site is better armed to safely and compliantly handle the cleanup complex’s transuranic radioactive waste.
A safe, reliable and accessible tool for opening waste drums and boxes, the new robotic arm began operating this month at the Advanced Mixed Waste Treatment Project’s (AMWTP) Treatment Facility.
It’s the first of two arms being installed, replacing the facility’s
original robotic arms used to examine, sort and treat much of the legacy
waste at AMWTP in the past 12 years.
The new arms are intended to create a safer work environment, enhance
productivity and reduce maintenance costs by an estimated 80 percent. In
2015, maintenance personnel entered the facility’s highly contaminated
boxlines more than 500 times, each time at a cost of at least $3,600.
Crews also report the new arm is easier on their hands and wrists.
Updating AMWTP’s capabilities is timely as retrieval crews remove the
last of the waste containers stored at the site for nearly a half
century.
The crews currently deal with the most challenging degraded
containers. Experience from retrieving more than 64,000 cubic meters of
stored waste has helped them prepare to remove the last 550 cubic
meters.
In preparing for the final retrieval work, crews reported the need for
equipment for increased ventilation to reduce potential contamination
levels. Their suggestions led EM to develop a system of pulleys and
rails to move a newly designed ventilation hood and hose inside the
inner contamination enclosure, a large, movable tent for seriously
degraded drums and boxes. The system increases air flow and prevents the
crews from sustaining strains and sprains caused by moving the
ventilation equipment.
AMWTP’s retrieval operations are scheduled for completion by May 2017.
Savannah River Site Begins Double-Stacking Waste Canisters
This
graphic shows the innovative concept for the canister double-stack
project. Each current canister position is being modified to accommodate
two canisters per existing slot.
AIKEN, S.C. – EM began double-stacking radioactive canisters recently at the Savannah River Site (SRS), part of an innovative effort to increase onsite interim storage capacity of glassified high-level waste.
A shielded canister transporter is used to stack two canisters in the
Glass Waste Storage Building (GWSB) 1 at the Defense Waste Processing
Facility (DWPF). Savannah River Remediation, the SRS liquid waste
contractor, is conducting the process.
To modify the canister positions to accommodate two, 10-foot tall
canisters, SRS employees developed a remote cutting tool to remove the
existing canister support crossbar.
SRR engineers created the tool for less than $120,000 — approximately 25 percent less expensive than commercial ones.
DOE-Savannah River Assistant Manager for Waste Disposition Jim Folk
said the project is a win for SRS and for saving taxpayer money.
“At DOE, we want to see safe, creative solutions to solve issues,”
Folk said. “Finding this new method for canister storage is a
game-changer in terms of finding new storage space that will save tens
of millions of dollars.”
The
first two canisters stacked on top of each other. In the bottom photo,
the first canister sits on the crossbar. In the top photo, the second
canister is positioned on top of the first canister.
SRS has removed more than 250 of 2,254 crossbars, and 150 of those
have been prepared for double-stacking, including installation of a new
support plate and shield plugs. The project will continue to modify
canister positions for up to eight years, as needed.
Double-stacking increases the storage capacity in GWSB 1 from 2,254
slots to 4,508 slots, creating adequate safe interim canister storage
until at least fiscal 2029 and postponing the expense of another storage
facility estimated to cost $74 million.
The radioactive canisters contain vitrified waste produced at DWPF.
High-level waste from SRS waste tanks is received at DWPF, mixed with a
borosilicate glass and heated to create a molten glass, which hardens
when poured inside the stainless steel canister. The canister is
temporarily sealed, the exterior is decontaminated, and a weld seals the
canister prior to storage transport.
The canisters are destined for a future federal repository, but pose
no technical or radiological issues staying at SRS in this interim
double-stack storage arrangement, according to engineering studies.
Hanford Site Technology Completes Cleanup to Protect Groundwater
Equipment used in soil vapor extraction was used to reduce the level of carbon tetrachloride on the Hanford Site.
RICHLAND, Wash. –
Regulators have approved the completion of a cleanup project on the
Hanford Site that began nearly 25 years ago that successfully removed
nearly 90 tons of deep-soil contamination and reduced groundwater risk
using a remediation technology known as soil vapor extraction.
EM’s Richland Operations Office
(RL) and contractor CH2M HILL Plateau Remediation Company (CH2M)
employed the technology to clear contamination by the chemical carbon
tetrachloride, which was used in Cold War plutonium processing
operations. It spread to an area approximately three-fourths of a square
mile and approximately 200 feet in the ground in the 200 West Area.
“This is a major accomplishment and success in our primary goal of
protecting the groundwater, which also protects the Columbia River,”
said Michael Cline, director of the RL soil and groundwater division.
Nearly 90 tons of contamination has been removed since workers began
operating the soil vapor extraction system to clean up carbon
tetrachloride in 1992.
The system was shut down in 2012 after carbon tetrachloride levels
were below final cleanup levels. A study performed from 2012 through
2015 showed the chemical was sufficiently removed, leaving no continuing
source.
The U.S. Environmental Protection Agency approved a soil vapor
extraction action report in August, completing all actions associated
with removal of carbon tetrachloride in that area.
“Our team of experts worked to track the contamination and maintain
the systems to assure removal of the largest amount of contamination
possible,” said Karen Wiemelt, vice president of CH2M’s Soil and
Groundwater Remediation Project. “Due to the expertise of our team and
other support groups we achieved the legal cleanup level for carbon
tetrachloride and were able to permanently end soil vapor extraction
operations.”
Removal of contamination from the vadose zone was crucial because it
reduced the amount of contamination reaching the groundwater.
Progress Moves West Valley Closer to Finishing Canister Relocation Project
Workers place a vertical storage cask liner on a construction pad.
WEST VALLEY, N.Y. – EM’s West Valley Demonstration Project (WVDP) is about 70 percent complete toward relocating all high-level waste canisters from a building to be demolished.
The site’s High-Level Waste Relocation Project has safety relocated
195 of the 278 canisters and is on track to move the rest of them to an
interim dry storage facility before the end of 2016, nearly one year
ahead of schedule.
The canisters must be moved from a former chemical processing cell in
the Main Plant Process Building before WVDP and contractor CH2M HILL
BWXT West Valley can demolish that building and the Vitrification
Facility.
The relocation project, which began in November 2015, marked the first
time vitrified high-level waste was relocated for onsite interim
storage in the U.S.
The canisters are loaded into vertical storage casks. Nearly 40 casks,
each weighing about 88 tons, have been moved about a half mile away to
the onsite interim storage pad for eventual disposal offsite.
NAC International, a U.S. supplier of dry storage technology and
services to the nuclear industry, constructed all 56 casks for the
project. With a design life of at least 50 years, each cask was built
onsite, constructed of 20-inch-thick reinforced concrete and containing
4-inch-thick stainless steel liners. Their design is based on spent
nuclear fuel dry cask storage systems used throughout the world, with
modifications for long-term storage of vitrified high-level waste.
The company previously developed 10 major Nuclear Regulatory
Commission (NRC)-licensed systems and the first storage and transport
canister-based system fully approved by the NRC.
The NAC team, including subcontractors NAES Constructors and local
craft, Petersen Industries and Lift-Systems, partnered to provide WVDP’s
solutions for interim storage and future shipment of the high-level
waste for disposal.
Watch this video of workers constructing the casks and learn more about the project.
Hanford Site Technology Completes Cleanup to Protect Groundwater
Equipment used in soil vapor extraction was used to reduce the level of carbon tetrachloride on the Hanford Site.
RICHLAND, Wash. –
Regulators have approved the completion of a cleanup project on the
Hanford Site that began nearly 25 years ago that successfully removed
nearly 90 tons of deep-soil contamination and reduced groundwater risk
using a remediation technology known as soil vapor extraction.
EM’s Richland Operations Office
(RL) and contractor CH2M HILL Plateau Remediation Company (CH2M)
employed the technology to clear contamination by the chemical carbon
tetrachloride, which was used in Cold War plutonium processing
operations. It spread to an area approximately three-fourths of a square
mile and approximately 200 feet in the ground in the 200 West Area.
“This is a major accomplishment and success in our primary goal of
protecting the groundwater, which also protects the Columbia River,”
said Michael Cline, director of the RL soil and groundwater division.
Nearly 90 tons of contamination has been removed since workers began
operating the soil vapor extraction system to clean up carbon
tetrachloride in 1992.
The system was shut down in 2012 after carbon tetrachloride levels
were below final cleanup levels. A study performed from 2012 through
2015 showed the chemical was sufficiently removed, leaving no continuing
source.
The U.S. Environmental Protection Agency approved a soil vapor
extraction action report in August, completing all actions associated
with removal of carbon tetrachloride in that area.
“Our team of experts worked to track the contamination and maintain
the systems to assure removal of the largest amount of contamination
possible,” said Karen Wiemelt, vice president of CH2M’s Soil and
Groundwater Remediation Project. “Due to the expertise of our team and
other support groups we achieved the legal cleanup level for carbon
tetrachloride and were able to permanently end soil vapor extraction
operations.”
Removal of contamination from the vadose zone was crucial because it
reduced the amount of contamination reaching the groundwater.
|
Michele Kearney's Nuclear Wire
Major Energy and Environmental News and Commentary affecting the Nuclear Industry.
Monday, October 17, 2016
EM Update | Vol. 8, Issue 19 | Oct. 17, 2016
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment