Regulator details Taishan 1 commissioning schedule
Regulator details Taishan 1 commissioning schedule: Unit 1 of the Taishan nuclear power plant is expected to be connected to the grid next month and achieve full-power operation by September, according to China's nuclear safety regulator. The unit, which achieved first criticality earlier this month, is expected to become the first EPR reactor to enter commercial operation, which it is scheduled to later this year.