Michele Kearney's Nuclear Wire

Major Energy and Environmental News and Commentary affecting the Nuclear Industry.

Tuesday, June 16, 2020

EM Update June 16, 2020

banner
The DOE Office of Legacy Management is set to assume long-term stewardship responsibility for 70 sites — represented by the yellow dots in this map — on the Nevada Test and Training Range where the EM Nevada Program completed environmental corrective actions in accordance with the Federal Facility Agreement and Consent Order.

LAS VEGAS – The EM Nevada Program and DOE Office of Legacy Management (LM) are nearing completion of a transfer of long-term stewardship responsibilities for 70 sites on the Nevada Test and Training Range (NTTR), including the Tonopah Test Range (TTR).
The transfer from EM to LM — among EM's ambitious priorities for 2020 — is expected to occur by Sept. 30.
"In partnership with the Office of Legacy Management and our lead environmental program services contractor, Navarro Research and Engineering, the EM Nevada Program is proud to be advancing the transfer of these sites,” EM Nevada Program Manager Rob Boehlecke said. “We fully expect to complete the transfer on time and on budget. This progress supports our federal cleanup mission and shows firsthand what can be accomplished when a dedicated team works together to accomplish a goal.”
The transfer process also involves the review and transmission of more than 7,200 documents and records from the EM Nevada Program to LM. Once the transfer is complete, LM will assume responsibility for long-term surveillance and maintenance of the sites in perpetuity.
In accordance with the Federal Facility Agreement and Consent Order (FFACO), the EM Nevada Program recently completed cleanup at sites on NTTR where contaminated soil and debris resulted from historic nuclear weapons testing and support activities. FFACO is a legally-binding agreement signed in 1996 that outlines a schedule of cleanup and monitoring commitments.
In the 1960s, sites at the NTTR were used to test nuclear weapons to determine if they could be accidentally set off and produce a nuclear yield. These experiments resulted in the contamination of soil and debris. During recently completed cleanup of these sites, contaminated soil and debris were transported to the Nevada National Security Site for permanent disposal.
For more information on the EM Nevada Program’s environmental restoration activities, click here
-Contributor: Michelle French


Oak Ridge Marks Another Teardown on Path to Vision 2020

p
Demolition begins on Building K-2500-H. The facility was located near the massive K-25 gaseous diffusion building and supported demolition efforts for that project.

OAK RIDGE, Tenn. – The Oak Ridge Office of Environmental Management (OREM) has conducted large-scale demolition at the East Tennessee Technology Park (ETTP) for nearly 15 years.
OREM and its contractor UCOR are nearing completion of teardowns there, and one facility they recently demolished had supported demolition work over the years.
Crews took down K-2500-H, also known as the Segmentation Shop. Contaminated equipment, piping, and other items generated by demolition projects were sent to the facility to be prepared for shipment for disposal.
Constructed in 2007 near the massive K-25 gaseous diffusion building, the Segmentation Shop was used to process items from K-25, the K-27 gaseous diffusion building, and other facilities that once supported the site’s uranium enrichment operations.
“The Segmentation Shop served a crucial purpose, allowing for efficient disposal of a variety of components pulled from various buildings,” said James Daffron, acting ETTP portfolio federal project director. “The fact that it is no longer needed highlights how close we are to completing site cleanup.”

p
A view of the remains from the demolition of the Segmentation Shop as Oak Ridge crews come closer to achieving Vision 2020. Cleanup efforts at the East Tennessee Technology Park will remove more than 13 million square feet of facilities.

While crews have completed demolition of all facilities that previously supported uranium enrichment operations, the Segmentation Shop became the latest in a long list of unneeded buildings that crews have removed at ETTP.
Only a handful of unneeded structures remain at the site. Demolition and major cleanup activities are expected to be completed at ETTP this year — a goal known as Vision 2020. It will account for the elimination of more than 13 million square feet, marking the first time in the world an entire uranium enrichment complex is removed. More than 12 million square feet of the complex has been removed already.
OREM and UCOR are working together to transform ETTP into a multi-use industrial park, national park, and conservation area for the community. That vision has already started to become a reality. OREM has transferred almost 1,300 acres at ETTP for economic development, with another 600 acres slated for transfer in the years ahead. OREM has also set aside more than 100 acres for historic preservation and placed more than 3,000 acres in conservation for community recreational use.
-Contributor: Wayne McKinney


EM Names New WIPP, Los Alamos Managers, Deputy Assistant Secretary for Safety, Security

EM has named new managers for the Carlsbad and Los Alamos field offices, and a new Deputy Assistant Secretary for Safety, Security, and Quality Assurance, among leadership updates at its sites and at headquarters.
Reinhard Knerr has been selected as manager of the Carlsbad Field Office (CBFO), where he will oversee operations at the Waste Isolation Pilot Plant (WIPP). He will transition from his current role as DUF6 Federal Project Director at the Portsmouth/Paducah Project Office where he supervises the depleted uranium hexafluoride (DUF6) conversion facilities at the Portsmouth, Ohio and Paducah, Kentucky sites.
Knerr has held leadership and strategic planning roles at the Paducah site since 2004, including managing environmental remediation work, transitioning the site’s gaseous diffusion plant from the United States Enrichment Corporation back to the Department of Energy, and initiating utility and infrastructure optimization projects. He also has served as the transuranic waste certification team leader at WIPP, and has over nine years of experience as a nuclear criticality safety engineer supporting contractor operations at the National Nuclear Security Administration’s Pantex Plant. Knerr holds a Bachelor of Science in nuclear engineering from the Pennsylvania State University.



At Carlsbad, Knerr will replace Greg Sosson, who has served as acting manager since December 2019. Sosson will return to EM headquarters to serve as Deputy Assistant Secretary for Safety, Security, and Quality Assurance. That position holds broad responsibility for overseeing the development of strategies, policy, and guidance for safety, security, and emergency preparedness to support the EM mission.
Sosson previously held the position of Associate Deputy Assistant Secretary for Field Operations Oversight at EM headquarters. Prior to joining DOE, Sosson was in the commercial nuclear industry for 28 years in senior operations and engineering positions with a focus on safe and efficient mission accomplishment, including 10 years as a senior reactor operator. He also spent 10 years as a light and mechanized infantry officer in the Army Reserve and National Guard. Sosson holds a Bachelor of Science in mechanical engineering from the Pennsylvania State University and a Master of Business Administration from Saint Joseph’s University. He is a licensed professional engineer.
Mike Mikolanis, who has been serving as Acting Deputy Assistant Secretary for Safety, Security, and Quality Assurance, will return to his role as assistant manager for nuclear material stabilization at the DOE-Savannah River Operations Office (DOE-SR).




Kirk Lachman has been selected as manager of the EM-Los Alamos Field Office, following a tenure as deputy manager and acting manager of CBFO. Before joining CBFO, Lachman was the Deputy Chief for Field Operations at EM headquarters. He has served in a variety of line management and safety oversight positions from 2010-2017 at the Nevada Field Office. He served from 2005 until 2010 as the engineering design group supervisor for the Office of Civilian Radioactive Waste Management in Las Vegas.
Lachman graduated from the DOE Senior Executive Service Candidate Development Program as well as the Harvard Senior Executive Fellows Program. He has a Bachelor of Science in chemical engineering from the University of Nebraska and a Master of Science in mechanical engineering from Colorado State University.
Lachman will replace Thomas Johnson, who has served as acting manager of EM-Los Alamos since March. Johnson will return to the Savannah River Site, where he serves as deputy manager of DOE-SR. In that role, Johnson has broad leadership responsibility for approximately $1 billion in annual operating and construction activities at SRS in the areas of environmental stewardship, and nuclear materials processing and disposition.


Hanford Marks 25 Years of Successfully Treating Wastewater

p
A view of the Effluent Treatment Facility’s process floor. Since 1995, the facility has processed more than 330 million gallons of contaminated wastewater to remove radioactive and chemical waste.

RICHLAND, Wash. – A significant component of EM’s complex chain of Hanford Site waste treatment facilities is marking a quarter century of safely treating contaminated wastewater while stretching the storage capacity of underground double-shell tanks.
The “Liquid Waste Processing Facilities” is a term used to collectively describe four primary facilities that work together to store, treat, and dispose of large volumes of liquid waste from around the site. The four facilities are the Liquid Effluent Retention Facility, Effluent Treatment Facility (ETF), Treated Effluent Disposal Facility, and the State-Approved Land Disposal Site.
Since 1995, the four facilities have processed more than 330 million gallons of contaminated wastewater to remove radioactive and chemical waste, primarily from the 242-A Evaporator. That equipment boils liquid tank waste to evaporate water, also called effluent, to reduce the volume of waste stored in Hanford’s underground tanks. Waste volume reduction is also critical for single-shell tank waste retrievals to double-shell tanks.
“Continued operations and volume management are important to meeting the Hanford mission need,” said Richard Valle, Tank Farm program manager.

p
Two new vessels were installed in the Effluent Treatment Facility in 2019. The facility is undergoing upgrades as it prepares to support Direct-Feed Low-Activity Waste operations to begin by the end of 2023.

The Liquid Effluent Retention Facility is currently designed to store about 23 million gallons of liquid waste until it can be processed at the ETF. The ETF processes the liquid waste to remove chemical and radioactive contaminants. Treated hazardous and radioactive effluent from ETF is then discharged to the State-Approved Land Disposal Site. The Treated Effluent Disposal Facility collects nonhazardous and nonradioactive treated wastewaters that are pumped to two infiltration basins on the site.
“In 2019, the ETF treated 3.4 million gallons of contaminated wastewater, exceeding its goal for the year by 1.4 million gallons,” said Brandon McFerran, ETF manager for Washington River Protection Solutions, EM’s Hanford tank operations contractor.
The ETF is undergoing upgrades to improve operations and reliability as crews prepare it to support Direct-Feed Low-Activity Waste operations. The ETF is part of the planned 24/7 conversion of liquid waste to a safe solidified glass form in the new Waste Treatment and Immobilization Plant.
-Contributor: Michael Butler


Spent Nuclear Fuel Transfers Support EM’s Commitment to State of Idaho

p
EM workers use a crane to lower a canister filled with spent nuclear fuel into a liner inside the Radioactive Scrap and Waste Facility at the Idaho National Laboratory Site.

IDAHO FALLS, Idaho – Crews recently completed the first two of nearly 40 shipments of spent nuclear fuel to a temporary storage area at the Idaho National Laboratory (INL) Site planned for 2020, helping EM move toward meeting its commitment with the State of Idaho to transfer the material from wet to dry storage by 2023.
Spent nuclear fuel handlers and other employees with Fluor Idaho, EM’s INL Site cleanup contractor, retrieved the fuel from an underwater basin at Chemical Processing Plant (CPP)-666 at the Idaho Nuclear Technology and Engineering Center (INTEC). They transferred the fuel to a shipping cask, which was loaded onto a tractor trailer and transported to the Radioactive Scrap and Waste Facility (RSWF) at the Materials and Fuels Complex (MFC). The cask was then unloaded from the trailer, placed over below-ground steel fuel storage liners, and lowered into place.
The RSWF, measuring almost 450 feet long and 390 feet wide, was originally built to receive remote-handled transuranic waste. However, modifications allowed it to serve as a temporary storage area for the fuel.
“The first shipments went off perfectly,” said Russ Cottam, Fluor Idaho spent nuclear fuel manager. “Our crews had practiced the processes using a mock-up and used a mobile crane and forklift to simulate the conditions at the RSWF. The placement of fuel at RSWF went according to plan.”

p
Equipment operators move a cask filled with spent nuclear fuel to a storage liner at the Radioactive Scrap and Waste Facility.

Workers are scheduled to make as many as 38 additional shipments of the fuel from INTEC to RSWF this year, with shipments continuing into 2021.
Beginning in September last year, equipment operators, engineers, fuel handlers, fabricators, and others worked as a team to conduct mock-ups of the fuel transfers at INTEC. Using a cask assembly built by the INTEC fabrication shop and a cask designed by INTEC engineers, the team practiced the transfers.
“So many dedicated people were involved in this effort,” Cottam said. “Using a mock-up allowed the team to identify challenges, revise procedures, and perform the steps flawlessly. It was the epitome of a well thought-out and executed project.”
The fuel had originated from the Experimental Breeder Reactor-II (EBR-II) reactor, which operated at the former Argonne National Laboratory-West, now MFC, from 1964 until 1994. The reactor generated power for the INL and provided reactor research benefits. Spent nuclear fuel from EBR-II was transferred to wet storage at CPP-666 from 1986 to 1999.
The spent nuclear fuel basin at INTEC is now nearly 95 percent empty. Just two fuel types remain: EBR-II and Advanced Test Reactor (ATR). ATR fuel continues to be transferred to CPP-603 for dry storage.
-Contributor: Erik Simpson


Shift Technical Engineer Program Growing to Meet SRS Mission Needs

p
EM Update | Vol. 12, Issue 13 | June 16, 2020
GreenBar

EM Nevada Transfer of 70 Sites to Legacy Management Nearly Complete

p
p
Reinhard Knerr has been selected as manager of the Carlsbad Field Office.
Greg Sosson will serve as Deputy Assistant Secretary for Safety, Security, and Quality Assurance.

p
p
After serving as Acting Deputy Assistant Secretary for Safety, Security, and Quality Assurance, Mike Mikolanis will return to his role as assistant manager for nuclear material stabilization at the DOE-Savannah River Operations Office.
Kirk Lachman has been selected as manager of the EM-Los Alamos Field Office.

p
p

After serving as acting manager of the EM-Los Alamos Field Office, Thomas Johnson will return to the Savannah River Site, where he serves as deputy manager of the DOE-Savannah River Operations Office.
John Mills conducts plant gauge checks at the Defense Waste Processing Facility as part of his job as a shift technical engineer for Savannah River Remediation at the Savannah River Site.

AIKEN, S.C. – A team of technical engineers is among the many groups growing to support the increased pace of liquid waste operations at EM’s Savannah River Site (SRS).
These engineers with SRS liquid waste contractor Savannah River Remediation (SRR) play a key role in daily operations at liquid waste facilities. As the engineering point of contact on each shift, they work at the Defense Waste Processing Facility (DWPF) and Tank Farm facilities, home to the underground waste tanks, helping ensure safe operations, making critical decisions in the field, and resolving emergent plant issues.
There are currently two shift technical engineers per shift covering the Tank Farm facilities and DWPF, and SRR plans to increase it to three per shift to provide staffing for the ramped-up waste processing expected to support the new Salt Waste Processing Facility (SWPF). SWPF is the EM facility that will process the remaining salt waste at SRS, which makes up about 90 percent of the remaining radioactive waste stored in underground tanks.
“With SWPF coming online, there will be more waste transfers, procedure changes, and emergent issues, and so there is a need to evaluate current shift technical engineer staffing,” SRR President and Project Manager Phil Breidenbach said. “The additional technical engineers will provide increased capability for solving emergent issues on shift without detracting from their primary role, which is to ensure compliance with the safety basis.”
More than 14 engineers have been promoted to shift technical engineer roles over the last four years, and there are currently 25 in the program — nine of which are training. Because of the high level of facility knowledge required, the training and qualification process to become a shift technical engineer is rigorous. It’s a four-part process: prerequisites, additional classroom training, on-the-job training, and a demanding oral examination. It usually takes about a year to become qualified.
“It is important to the overall liquid waste mission and day-to-day operations to identify key people who will perform well as a shift technical engineer and train them early and thoroughly to take on this vital role,” Breidenbach said.
For SRR shift technical engineer Annah Garrison, the best part of the job is the people.
“Working on shift you get to know the people well, and it feels like family,” said Garrison, who has worked in the position in the tank facilities for just over two years. “We look out for each other, and we work together to do the right thing. My shift always challenges me and motivates me to improve. It feels good to work as a team to accomplish something together.”
-Contributor: Colleen Hart

Like EM on Facebook at: https://www.facebook.com/DOEEnvironmentalManagement


No comments:

Post a Comment