The
Department of Energy has approved a new plan to deal with a stockpile
of uranium-233 at Oak Ridge National Laboratory for an estimated $511
million.
Using
hot cells at ORNL's Building 2026 instead of erecting a new facility,
the plan is expected to process the material by 2018 instead of 2029 and
halves the cost of the previous plan, estimated at $1.1 billion, the
Knoxville News Sentinel reported. Oak Ridge recently received formal
approval to begin the processing phase of the project.
The
Atomic Energy Commission produced the U-233 in the 1960s during
experiments looking into its potential in commercial reactors. Its
disposition is a high priority for the lab because the material can also
be used to make nuclear weapons. In 2003, the lab contracted with a
consortium called Isotek to extract medical isotopes from the material
and downblend it with depleted uranium for disposal off site. Over the
years, the isotope extraction effort was abandoned and costs escalated
from the original $128 million price tag.