9, 2014
Source: U.S. Energy Information Administration, based on U.S. Nuclear Regulatory Commission
Following a two-year hiatus, the U.S. Nuclear Regulatory Commission
(NRC) has resumed issuing license renewals for nuclear power plants. On
October 20, the NRC renewed the operating licenses for Limerick
Generating Station Units 1 and 2, located northwest of Philadelphia,
extending their license expiration dates by 20 years, to 2044 and 2049,
respectively. With this action, the NRC has granted license renewals
providing a 20-year extension to a total of 74 of the 100 operating
reactors in the United States. Nuclear power accounted for 20% of total
power sector electricity generation in 2013.
NRC has the authority to issue initial operating licenses for
commercial nuclear power plants for a period of 40 years. The decision
to apply for an operating license renewal is made by nuclear power plant
owners, and it is typically based on economics and the ability to meet
NRC regulations. Operating licenses are
renewed
by NRC for a period of 20 years. To date, no applications for a
second, or subsequent, license renewal, which could extend nuclear plant
operating lives to 80 years, have been filed.
Renewing an operating license is contingent on several factors,
including the safe management and disposal of waste. The NRC must
determine that it has reasonable confidence that spent nuclear fuel can
and will, in due course, be disposed of safely. This is known as waste
confidence. Waste confidence enables the NRC to license new reactors or
renew their operating licenses without examining the effects of
extended waste storage for each individual site pending ultimate
disposal.
In June 2012, following the termination of the repository program at
Yucca Mountain, the U.S. Court of Appeals for the District of Columbia
Circuit struck down certain provisions of NRC's Waste Confidence Rule
and stated that NRC should have analyzed the environmental consequences
of never building a permanent waste repository. In response, the NRC
issued an order in August 2012 that suspended actions related to issuing
license renewals as well as new operating licenses, although the
nuclear power industry continued to submit applications for license
renewals. On September 18, 2014, the NRC issued the revised and renamed
Continued Storage of Spent Nuclear Fuel
rule, which became effective on October 20. With the issuance of the
revised rule, the NRC may now resume issuing license renewals as well as
new operating licenses.
NRC is currently reviewing license renewal applications for 17
reactors, including one for Indian Point Unit 2. Although the September
2013 expiration date of the original 40-year operating license for that
plant is already past, NRC rules allow for continued operation of a
reactor until the NRC completes its review of a pending license renewal
if the application was submitted at least five years before the current
license expires. Indian Point Unit 2, located on the Hudson River north
of New York City, currently continues to operate according to this
process, known as timely renewal. To date, Indian Point Unit 2 is the
only reactor that has entered the process of timely renewal.
NRC also expects to receive license renewal applications from seven
more reactors between 2015 and 2018. Plans for only one plant have not
yet been announced; however, license expiration for this plant is not a
near-term issue.
Source: U.S. Energy Information Administration, based on U.S. Nuclear Regulatory Commission
Principal contributor: Nancy Slater-Thompson