Michele Kearney's Nuclear Wire

Major Energy and Environmental News and Commentary affecting the Nuclear Industry.

Monday, May 2, 2011

Press Release (May 02,2011) Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, May 2)

Press Release (May 02,2011)
Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, May 2)
*New updates are underlined

All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down.

Unit 1 (Shut down)
- Explosive sound and white smoke were confirmed after the big quake 
  occurred at 3:36 pm on March 12. It was assumed to be hydrogen explosion.
- At approximately 2:30 am on March 23, seawater injection to the nuclear 
  reactor through the feed water system was initiated.
- From 3:37 pm on March 25, we started injecting freshwater and are now 
  injecting fresh water by a motor driven pump powered by the off-site 
  transmission line. From on April 27, we have increased the amount of 
  injecting freshwater from approximately 6 m3/h to approximately 14 m3/h. 
  At 10:14 am on April 29, we put the amount of injecting freshwater back 
  to approximately 6 m3/h.
- As it is suspected that hydrogen gas is accumulated inside reactor 
  containment vessel, we commenced the valve opening operation concerning 
  injection of nitrogen gas into the reactor container vessel at 10:30 pm 
  April 6th and commenced injection at 1:31am April 7.

Unit 2 (Shut down)
- At approximately 6:00 am on March 15, an abnormal noise began emanating 
  from nearby Pressure Suppression Chamber and the pressure within the 
  chamber decreased. 
- From 10:10 am on March 26, we started injecting freshwater to the reactor 
  and are now injecting fresh water by a motor driven pump powered by the 
  off-site transmission line.

Unit 3 (Shut down)
- Explosive sound and white smoke were confirmed at approximately 11:01am 
  on March 14. It was assumed to be hydrogen explosion.
- From 6:02 pm on March 25, we started injecting fresh water to the reactor 
  and are now injecting fresh water by a motor driven pump powered by the 
  off-site transmission line.

Unit 4 (outage due to regular inspection)
- At approximately 6:00 am on March 15, we confirmed the explosive sound 
  and the sustained damage around the 5th floor rooftop area of the Nuclear 
  Reactor Building.
- At this moment, we do not consider any reactor coolant leakage inside the 
  reactor happened.

Unit 5 (outage due to regular inspection)
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 5:00 am on March 19, we started the Residual Heat Removal System Pump 
  (C) in order to cool the spent fuel pool.
- At 2:30 pm on March 20, the reactor achieved reactor cold shutdown. 
- At this moment, we do not consider any reactor coolant leakage inside 
  the reactor happened.

Unit 6 (outage due to regular inspection)
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 10:14 pm on March 19, we started the Residual Heat Removal System 
  Pump (B) of Unit 6 in order to cool the spent fuel pool.
- At 7:27 pm on March 20, the reactor achieved reactor cold shutdown.  
- At this moment, we do not consider any reactor coolant leakage inside 
  the reactor happened.

Operation for cooling the spent fuel pools
- From 10:05 am to 11:40 am, May 2, water injection to Unit 2 was 
  conducted by temporary motor driven pump. 
- We will continuously conduct further water spray depending on the 
  conditions of spent fuel pools, if needed.

Others
- Regarding the transfer of high level radioactive wastewater in Unit 2 to 
  the Centralized Radiation Waste Treatment Facility, while we temporarily 
  suspended transfer due to the inspection of transferring facilities at 
  9:16 am on April 29, transfer was restarted at 2:05pm on April 30.
- The transfer of accumulated water in Unit 6 turbine building to a 
  temporary tank was conducted from 2:00 pm to 5:00 pm on May 1 and the 
  transfer was restarted from 10:00 am, May 2.
- We will continue to take all measures to ensure the safety and to 
  continue monitoring the surrounding environment around the power station.

No comments:

Post a Comment