Edison's San Onofre plan could make things worse, consultant says [Updated]
A consultant who has criticized Southern California Edison's handling
of the troubled San Onofre nuclear plant issued a report Tuesday saying
the utility's proposed solution for bringing the plant back online could
make the issues worse.
Plan to cut tube wear falls short at Cal nuke site
msnbc.com - 1 hour agoLOS ANGELES — A $670 million overhaul at Edison International's San
Onofre nuclear plant in California was expressly intended to avoid the
types of ailments that have sidelined its twin reactors. An overriding
goal for a team of engineers who worked on ...
Boxer presses NRC on questions at Calif nuke plant
BusinessWeek -
By MICHAEL R. BLOOD California Sen. Barbara Boxer is pushing federal
regulators for details about the troubled steam generators at the idled
San Onofre nuclear power plant. Boxer asked Nuclear Regulatory
Commission Chairman Gregory Jaczko Tuesday for ...
Activists' study doubts safety at Calif nuke plant
CBS News -
LOS ANGELES — An environmental group says that running California's San
Onofre nuclear plant at reduced power will not solve problems with
badly worn tubing that have kept the twin reactors offline for months.
Southern California Edison this month ...
San Onofre Power Plant Study Finds That Running At Reduced Power Could Worsen ...
Huffington Post -
By MICHAEL R. BLOOD 05/15/12 01:34 PM ET LOS ANGELES — California Sen.
Barbara Boxer asked federal regulators Tuesday for details about the
troubled steam generators at the San Onofre nuclear power plant, where a
long-running probe into tube damage has ...
Edison, consultant spar over blame for San Onofre shutdown
Los Angeles Times - 18 hours ago
A document released Monday by the US Nuclear Regulatory Commission
shows that Southern California Edison informed the federal agency of a
number of planned design changes before it replaced the plant's four
steam generators.
Report questions San Onofre restart plan
Report questions San Onofre restart plan
U-T San Diego -
Restarting the San Onofre nuclear plant at reduced power would not
resolve issues of rapid wear on steam generator tubes that have
sidelined the plant for more than three months, and might make matters
worse, says an analysis commissioned by an ...
Running San Onofre on reduced power could worsen damage
KABC - 2 hours agoSAN CLEMENTE, Calif. (KABC) -- There is concern about a plan to run
reactors at San Onofre at lower power. In a report Tuesday, the
environmental group Friends of the Earth said running the reactors at
reduced power could make damage at the plant even ...
Fairewinds report blows off steam generator safety claims at San Onofre
89.3 KPCC (blog) -
San Onofre is twisting in the breeze of the new Fairewinds safety
report released by activist group Friends of the Earth. The study raises
serious doubts about safety at the Southern California nuclear
facility, and says running at reduced power will ...
NRC Releases Missing Record on San Onofre Plant
NRC Releases Missing Record on San Onofre Plant
VoiceofOC - Federal regulators Monday
New Report Reveals Scale of Edison Steam Generator Failures at San Onofre ...
New Report Reveals Scale of Edison Steam Generator Failures at San Onofre ...
WASHINGTON, DC--(ENEWSPF)--May 15, 2012. Southern California Edison
avoided federal regulatory guidelines when replacing defective steam
generators at the San Onofre nuclear power plant -- a costly mistake
that can't be fixed by plugging the tubes that ...