Haiyang NPP AP1000 Unit 1 Succeeds in Dome Lifting
On December 15, after experiencing stressful one hour 51 minutes oflifting, moving, rotating, and a series of high-precision docking action, the world's first third-generation AP1000 automation projects, Haiyang nuclear power plant unit 1 constructed by China Nuclear Industry 24 Construction Co., Ltd. successfully complete dome lifting. It marks that most of the key nuclear components inside the island have been installed and will go into other parts of the installation and equipment commissioning part.
Top diameter of the round table-like dome is 21.5 meters and down diameter is 41.3 meters, with 10.95 meters high and 746.6 tons of weighing. The lifting condition of this hoisting has become the one with the biggest weight and the most complex one for Haiyang NPP by far. Haiyang NPP is the world’s first project that adopts AP1000 nuclear power technology and also China’s independent third-generation project contracted to be constructed by China Nuclear Industry 24 Construction Co., Ltd. At present, there is no domestic nuclear power plants have been built for reference.
Source: http://www.cnecc.com/g336/s1443/t13886.aspx
中核二四承建的海阳AP1000核电一号机组穹顶吊装成功 cnecc.com
12月15日清晨8点29分,经历紧张的1小时51分的起吊、
移动、旋转、对接等一系列高精度动作,由中核二四承建的世界首批第三代核电AP1000自主化依托项目——海阳核电一号机组穹顶吊装成功。
穹顶上口直径21.5米,下口直径41.3米,高10.95米,重746.6吨,呈圆台状。此次吊装是海阳核电迄今为止吊装工况最复杂、重量最大的一次吊
装。为确保吊装顺利进行,中核二四参建人员凝心聚力,奋勇拼搏,以福清核岛穹顶吊装的良好实践为基础,...
No comments:
Post a Comment