Michele Kearney's Nuclear Wire

Major Energy and Environmental News and Commentary affecting the Nuclear Industry.

Tuesday, May 19, 2020

Leningrad II-2 start-up postponed to April 2021 : Covid-19 - World Nuclear News

Leningrad II-2 start-up postponed to April 2021 : Covid-19 - World Nuclear News: Rosatom has applied to delay by two months the commissioning of unit 2 of the Leningrad II nuclear power plant in western Russian owing to the departure from the country of foreign workers installing diesel generators at the site. According to a report by Russian newspaper Kommersant yesterday, Rosatom considers their exit - owing to safety considerations amid the coronavirus pandemic - to be force majeure and has requested to be released from any fine for not being able to meet its obligations to add the unit's generating capacity to the wholesale market.

No comments:

Post a Comment