A view of the former K-832 Basin at Oak Ridge before workers removed it.
A view of the former K-832 Basin area after workers removed the basin and backfilled and seeded the site.
Crews finished taking down the last of the 11 main buildings
in the Poplar Creek area in September 2019. That effort, which began in
2017, eliminated the most contaminated facilities remaining at the ETTP
and removed the last of the buildings associated with the site’s
gaseous diffusion uranium enrichment operations.
“Completion
of the K-832 basin project wraps up a significant soil remediation
effort in the Poplar Creek area, and it greatly enhances the aesthetics
to the surrounding economic development parcels,” Daffron said.
The
Oak Ridge Office of Environmental Management (OREM) and UCOR are
working together to transform ETTP into a multi-use industrial park,
national park, and conservation area for the community. That vision has
already started to become a reality. OREM has transferred almost 1,300
acres at ETTP for economic development, with another 600 acres slated
for transfer in the years ahead. OREM has also set aside more than 100
acres for historic preservation and placed more than 3,000 acres in
conservation for community recreational use.
-Contributor: Wayne McKinney
Mock-up to Support Stabilization of Three At-Risk Structures on Hanford Site
The
EM Richland Operations Office and its contractor CH2M HILL Plateau
Remediation Company are building an off-site mock-up of a conveyance
system that will be used to move engineered grout from trucks into three at-risk underground structures on the Hanford Site.
RICHLAND, Wash. – As the Hanford Site continues a phased remobilization of site operations, EM Richland Operations Office
(RL) and its contractor CH2M HILL Plateau Remediation Company (CHPRC)
recently began designing and constructing a full-scale off-site mock-up
to support the stabilization of three underground structures with engineered grout.
The three structures, located near the former Plutonium Finishing Plant,
received liquid waste during Hanford’s plutonium production operations
and contain residual radioactive and chemical contamination. A 2019
report indicates the structures are at risk of age-related failure.
“We
are making good progress on the mock-up for the stabilization project
following appropriate health and safety protocols as we continue our
phased remobilization,” said Al Farabee, RL assistant manager for the
river and plateau. “This work is critical to Hanford’s mission to reduce
risk to workers, the public, and the environment.”
Nuclear
Waste Partnership (NWP) President and Project Manager Sean Dunagan,
center, helps unfurl the Voluntary Protection Program (VPP) Star site
flag during a brief ceremony at the Waste Isolation Pilot Plant (WIPP)
in late June. Also pictured, from left, are Paulette Henry, WIPP VPP
Committee member; Rick Fuentes, United Steel Workers Union president;
Tim Taulbee, NWP environment, safety and health manager; and Frank
Methola, United Government Security Officers Union president.
EM contractors at the Waste Isolation Pilot Plant (WIPP) and Savannah River Site (SRS) were recently awarded Star status for safety and health advances through the DOE’s Voluntary Protection Program (VPP).
“This
is a very significant milestone,” DOE Carlsbad Field Office Acting
Manager Greg Sosson said of Nuclear Waste Partnership (NWP), the WIPP
management and operations contractor. “I’m looking forward to the
continued success at WIPP that is enabled by the behaviors needed to
attain this recognition.”
Working
through cooperative efforts among labor, management, and government at
DOE contractor sites, the VPP promotes improved health and safety
performance. The Star status is for DOE contractors whose injury rates
meet the DOE standard of 50 percent below industry average, who perform
mentoring and outreach activities, and exemplify management leadership,
employee involvement, worksite analysis, hazard prevention and control,
and safety and health training.
After
separate fire and radiological events in 2014, WIPP implemented a
variety of safety improvements and received VPP Merit status in 2015.
Last year, a DOE VPP team spoke highly of the changes that had been
made, noting that it would return to WIPP in 2020 to ensure their
permanence. The team visited again in January and recommended Star
status for the site.
“Safety
improvements that began in 2018 have matured, and Nuclear Waste
Partnership has demonstrated its commitment to making those improvements
permanent and earned the workers’ trust,” the team’s report states.
“We
stand ready to assist you as you continue in your pursuit of
excellence,” DOE Associate Under Secretary for Environment, Health,
Safety and Security Matthew Moury wrote in the Star status notification
letter to the WIPP contractor.
“This
is an impressive accomplishment and milestone,” NWP President and
Project Manager Sean Dunagan said. “I would like to thank our employees
for making this achievement possible through their dedication to
ensuring that safety is No. 1 at WIPP.”
The
Voluntary Protection Program (VPP) flag continues to fly in front of
the Savannah River Site’s Defense Waste Processing Facility, operated by
Savannah River Remediation.
In
the announcement to Savannah River Remediation (SRR), EM’s liquid waste
contractor at SRS, Moury congratulated employees ”for your pursuit of
excellence in health and safety and your efforts to retain Star status
in the Department of Energy’s Voluntary Protection Program.”
The DOE-VPP team completed its two-week onsite review of SRR in February.
“After
reviewing our programs, talking to our personnel, and watching work
being completed, the VPP team reached the conclusion that SRR should be
recertified as a Star site,” said Mark Schmitz, SRR chief operating
officer and deputy project manager. “Every team member takes our core
value of safety to heart and contributes to that success.”
For more information on DOE’s VPP Program, click here.
-Contributors: Colleen Hart, Victoria Parker
Spent Nuclear Fuel Transfers Allow INL to Continue Mission-Critical Work
A
shipment of spent nuclear fuel travels from the Advanced Test Reactor
Complex to the Idaho Nuclear Technology and Engineering Center.
IDAHO FALLS, Idaho – EM
and cleanup contractor Fluor Idaho recently partnered with Battelle
Energy Alliance (BEA) to perform transfers of spent nuclear fuel at the Idaho National Laboratory (INL) Site.
The shipments from the Advanced Test Reactor (ATR) Complex to the Idaho Nuclear Technology and Engineering Center (INTEC) allow BEA, which manages INL, to prepare for mission-critical work at the ATR.
Russ
Cottam, Fluor Idaho spent nuclear fuel projects manager, said the
shipments have been conducted safely and with a minimum staff to ensure
social distancing due to the COVID-19 pandemic. The fuel was transferred
from wet storage at the ATR canal to the Chemical Processing Plant
(CPP)-603 spent nuclear fuel storage facility, where it was placed in
dry storage.
“We exceeded our goal of 10 shipments this calendar year and completed the scope ahead of schedule," Cottam said.
Fluor
Idaho’s spent nuclear fuel program maximized CPP-603’s unused space so
the program can transfer the remaining fuel from the CPP-666 basin to
dry storage by 2023 to comply with an Idaho Settlement Agreement
milestone.
New
fuel buckets, fabricated by Fluor Idaho, allow 50 percent more ATR fuel
elements to be stacked in fuel canisters at CPP-603. The new buckets
are segmented differently than the previous ones, allowing fuel handlers
to stack fuel assemblies in different configurations, resulting in more
assemblies being loaded in the same amount of space.
With the new fuel buckets, CPP-603 can continue to accept the ATR fuel directly into dry storage for at least 10 more years.
-Contributor: Erik Simpson
SRS Workers Safely Demolish Two Contaminated Structures
Workers prepare
equipment removed from a recently demolished contaminated structure at
the Savannah River Site to be permanently encapsulated within
cement-like grout.
AIKEN, S.C. – EM
crews have demolished two small structures formerly used to measure the
flow of hazardous wastewater and obtain sample data within a process
sewer line at the Savannah River Site (SRS).
Not
much larger than a walk-in closet, each unit was built over an eight-
to 12-foot-deep concrete pit, providing a sample point to the sewer
line.
The
closure task team placed contaminated equipment and non-contaminated
process sampling equipment, such as piping, tanks, and pumps, into each
pit prior to permanently encapsulating them in cement-like grout.
Workers used 40 cubic yards of grout to fill the two pits and placed 16
cubic yards of concrete as a permanent barrier atop the grouted
structure, completing the closure process.
“Though
the first phase of the closure project was not large in size, it was
definitely important in that the two primary access points to the
contaminated sewer line have now been safely and permanently closed,”
said Andrew MacMillan, the project lead with EM contractor Savannah
River Nuclear Solutions.
The
remediation plan for this project was approved by the South Carolina
Department of Health and Environmental Control (SCDHEC). The 4,050-foot
sewer line, which runs under a high-traffic roadway at SRS, will be
closed to comply with the Resource Conservation and Recovery Act.
The
sewer line once carried contaminated process waste from F Canyon
operations to the F Area Seepage Basin, which is now closed. Sampling
wastewater from the sewer line ensured optimal flow of effluent leaving
the canyon and provided accurate measurement of the level of
radioactivity and other hazardous materials. Sampling of the F Canyon
wastewater began in the 1950s and ceased in 1988 when the sewer line was
taken out of service.
“This
SRS project represents the success that happens when different
organizations work together as a team with the common goal of protecting
human health and the environment, especially the employees and
surrounding communities,” said Keehna Frasier, project manager, SCDHEC
Division of Waste Management.
-Contributor: DT Townsend
Training, Planning Lead to Successful Sensor Removal from Hanford Tanks
Washington
River Protection Solutions workers use shielding to remove a highly
contaminated thermocouple from a Hanford tank farm. Planning and
mock-ups significantly reduced potential exposure risks while removing
thermocouples.
RICHLAND, Wash. – EM Hanford
tank operations contractor Washington River Protection Solutions is
preparing to retrieve radioactive and chemical waste from storage tanks
in the site’s A Tank Farm.
Removing
obstructions in the tanks that would interfere with retrieval
operations, such as old thermocouples, presents several hazards that can
be mitigated with specialized tools, techniques, and training and the
use of mock-ups.
Thermocouples
are temperature-sensing devices that help Hanford technicians monitor
conditions inside tanks. In addition to the radiological and industrial
hazards involved in removing contaminated equipment from tanks,
corrosion of the 50-foot-long thermocouples creates a risk they could
break apart during removal.
Earlier
this spring, workers removed damaged thermocouples used to measure
waste temperatures in Tanks A-101 and A-103. In these tanks, the lower
sections of the thermocouples were damaged, requiring the use of cutting
and clamping techniques to safely remove them.
“Various
shield designs and clamping techniques were tested during planning
mock-ups, which significantly mitigated the radiation hazards,” said
Christine Lobos, EM tank farm facility representative. “Our overall site
cleanup strategy is to focus consistently on safety of the workforce,
the public, and the environment while progressing our cleanup mission.”
To
protect workers, many weeks of planning and training in mock-up
conditions helped before crews retrieve the contaminated equipment from
the underground tanks.
“Each
tank presents its own set of challenges,” said Diego Arteaga,
contractor fieldwork supervisor. “The removal of the first thermocouple
at Tank A-103 required a complete design of clamps due to the
deterioration. Because of the training, we knew what to do and how to do
it safely.”
The
workers used high-pressure spray washes on the thermocouples at Tanks
A-101 and A-103 to reduce some of the radiation levels. The team then
cut the thermocouples into segments and lowered the corroded lower
segments to the tank floor. The remaining sections were removed from the
tanks, placed in shielded containers, and shipped to Hanford’s
Environmental Restoration Disposal Facility for disposal.
“Multiple
layers of safety were integrated into the retrieval work on the tanks,”
said Arteaga. “The team showed the value of preparation when doing
dangerous work and our work paid off.”
-Contributor: Peter Bengtson
West Valley Encases Building Slab With Fixative After Removing Asbestos
A
worker at the West Valley Demonstration Project applies a fixative to
the concrete slab of the former Main Plant Office Building to protect
employees from potential asbestos.
WEST VALLEY, N.Y. – An EM deactivation and demolition crew at the West Valley Demonstration Project (WVDP) recently encapsulated a concrete slab with a fixative after removing asbestos from it.
The concrete slab was the foundation for the former Main Plant Office Building, which workers demolished late last year, bringing EM’s total number of structures removed at WVDP to 66.
Workers
had safely removed asbestos-containing material from inside that
building prior to tearing it down. Built in 1964, the three-story,
3,760-square-foot facility was part of the original commercial nuclear
fuel reprocessing plant at the site.
“Our
team continues to leverage their combined knowledge and expertise to
safely complete the demolition, disposition, and restoration of
facilities no longer needed,” EM WVDP Director Bryan Bower said. “This
work will enhance safety efforts in preparation for the future
demolition of the Main Plant Process Building.”
Demolition of the Main Plant Process Building is an EM priority for 2020.
The
Main Plant Office Building was one of several Main Plant Process
Building support structures. The next ancillary building set for
demolition is a utility building. That teardown will occur after the
site transitions to Phase 2 of its COVID-19 Work Resumption Plan.
-Contributor: Joseph Pillittere
Workers Use Skill, Ingenuity to Install New Manipulators at Oak Ridge
Isotek
employees Shane Miles, left, and Ryan Souza stand behind a cutting tool
used to help install new remote manipulators in hot cells at Oak Ridge.
OAK RIDGE, Tenn. – Upgrades and construction are progressing at Building 2026 to prepare the facility to begin processing a high-dose portion of Oak Ridge’s uranium-233 inventory. That work will enable EM to convert the material into a disposal-ready form after extracting an unprecedented amount of thorium for next generation cancer research.
Oak
Ridge Office of Environmental Management (OREM) and contractor Isotek
are performing the work to support EM’s highest priority project at DOE’s Oak Ridge National Laboratory — to eliminate the inventory of uranium-233.
The
high-dose portion of the inventory must be processed in hot cells that
provide protective shielding and remote mechanical arms, known as
manipulators, to handle the material. First, however, those hot cells
require upgrades, including new remote manipulators. View a video
explaining the upgrades here.
Isotek employees Wes McCloud, Shane Miles, and Ryan Souza developed a tool to install the new hot cell manipulators.
Manipulators
must be installed without anyone entering the hot cells due to
contamination inside the cells. To accomplish this, the manipulators are
slid through a tube on the hot cell outer wall and clamped against that
wall.
The
Isotek employees learned that the tube needed to be shortened because
it extended beyond the wall on the inside of the hot cell. They planned
to insert a circular cutting tool from the non-contaminated side of the
tube to shorten it inside the hot cell.
Despite that challenge, the task became even more difficult.
“After about 30 minutes, the cutter would quit spinning,” Miles said. “If the cutter isn’t spinning, then it’s not cutting.”
Heat
generated from the rapid spinning of the cutter and the friction
against the tube caused part of the cutter to expand and jam itself
against the interior of the tube.
The
employees shaved down the expanding piece of the cutter to keep it from
making contact with the tube interior and attached shock-absorbing ball
bearings to it. These changes helped stabilize the cutter and reduce
friction while cutting.
The hot cells are scheduled to be ready for processing high-dose canisters later this year.
Isotek was processing low-dose canisters of uranium-233 in gloveboxes
before Oak Ridge entered essential mission-critical operations in
April. That work is scheduled to resume as operations ramp up in future
phases.
-Contributor: John Gray
Advance Agenda Available for 2020 National Cleanup Workshop
EM Update | Vol. 12, Issue 16 | July 7, 2020
|
Crews Remove Basin as Oak Ridge Heads Toward ETTP Cleanup Completion
OAK RIDGE, Tenn. – A basin that once held cooling water used in Oak Ridge’s former uranium enrichment operations has been removed from the East Tennessee Technology Park (ETTP), and now the site where it was located has been restored.
Workers
recently completed removal of the K-832 Basin in the Poplar Creek area
at ETTP. It was used in conjunction with a pumphouse and cooling tower,
both of which were demolished by EM crews in 2017.
The
below-ground basin contained more than 2 million gallons of
nonradioactive water that had to be pumped and treated. After Oak Ridge
cleanup contractor UCOR completed water and sludge removal and
demolished the basin, workers backfilled and seeded the site.
“The
K-832 Basin area now joins numerous other projects where we transformed
areas with old, contaminated, and dilapidated facilities or subsurface
structures into grassy fields for the site’s next chapter,” said James
Daffron, acting ETTP portfolio federal project director for Oak Ridge’s
EM program. “The landscape changes happening across ETTP are a testament
to how close we are to achieving Vision 2020.”
Among EM’s 2020 priorities, Vision 2020
is the cleanup program’s goal to complete all demolitions and major
cleanup at ETTP by the end of 2020. It will mark the first time in the
world an enrichment complex is cleaned and removed.
|
The
EM Richland Operations Office and its contractor CH2M HILL Plateau
Remediation Company are testing a conveyance system that will pump
engineered grout through more than 1,500 feet of pipe to three
underground at-risk structures at the Hanford Site, helping to keep
workers out of high-contamination areas.
Construction
of the mock-up includes a conveyance system that will be used to move
more than 4,500 cubic yards of engineered grout from trucks into the
structures. The grout will be pumped through more than 1,500 feet of
pipe, helping to keep workers out of high-contamination areas. Mock-ups
are used extensively at Hanford to allow crews to troubleshoot processes
and safely train on tools and equipment in a clean environment before
work begins in the field.
“The
conveyance system is going to help us tremendously because all three
structures are in high radiological areas,” said Delise Savior, CHPRC
project manager. “This will minimize our time in these areas while
allowing us to safely and efficiently stabilize the structures. Crews
will also monitor radiological conditions before and during work to
further ensure our workers and the environment are protected.”
The stabilization project is expected to be completed by the end of 2020.
Check out this video to see more about the engineering walk-down on the project.
Grout has been used to safely stabilize other structures
at Hanford, including a combined 44,000 cubic yards to stabilize two
waste storage tunnels next to the Plutonium Uranium Extraction Plant, or
PUREX, in 2017 and 2019.
-Contributor: Joan Lucas
|
WIPP, SRS Contractors Achieve Voluntary Protection Program Star Status |
An
advance agenda is now available for the 2020 National Cleanup Workshop
that will bring together top Department of Energy officials as well as
industry and state, tribal, and local government leaders to discuss
progress and opportunities in the EM cleanup mission.
The
sixth-annual workshop will be held Sept. 16-17 at the Hilton Alexandria
Mark Center in Alexandria, Virginia. The workshop is hosted by the
Energy Communities Alliance with the cooperation of EM and the Energy
Facility Contractors Group.
Confirmed
speakers so far include EM Senior Advisor William “Ike” White, EM
Principal Deputy Assistant Secretary Todd Shrader, and other EM
headquarters and site leaders.
Scheduled sessions will include:
The advance agenda for the 2020 National Cleanup Workshop can be found here.
More
than 800 attendees, including senior DOE executives, congressional
leaders, DOE contractors, and state, tribal, and local government
leaders, participated in the 2019 workshop — the largest EM-focused
gathering in the D.C. area last year. More information on past workshops
can be found here.
|
Like EM on Facebook at: https://www.facebook.com/
|
No comments:
Post a Comment