Further delay in commissioning of Finnish EPR : New Nuclear - World Nuclear News
Further delay in commissioning of Finnish EPR : New Nuclear - World Nuclear News: Fuel loading at the Olkiluoto 3 EPR will now not take place until March next year, according to a revised schedule provided to Finnish utility Teollisuuden Voima Oyj by the Areva-Siemens consortium. Grid connection is now scheduled for October 2021, with regular electricity production due to start in February 2022.