Fukushima - 18 March morning updates, radiation and tsunamisBarry Brook | 18 March 2011 at 10:57 AM | Categories: Hot News, Nuclear | URL: http://wp.me/piCIJ-14h |
Other points to note, as of the morning of Friday 18 March:
1. FEPC says the following:
Through visual surveys from the helicopter flying above the Unit 4 reactor secondary containment building on March 16, it was observed that water remained in the spent fuel pool. The helicopter was measuring radiation levels above Unit 4 reactor secondary containment building in preparation for water drops. This report has not been officially confirmed.2. WNN says:
The Ministry of Economy Trade and Industry said at 8.38pm that a cable was being laid to bring external power from transmission lines owned by Tohoku Electric Power Company. This was to be connected when radiation levels had died down after a planned venting operation at unit 2. In addition, one of the emergency diesel units can now be operated and will be used to supply unit 5 and 6 alternately to inject water to their used fuel pools. Later, the power will be used to top up water in the reactor vessels...3. The two statements above are supported by the updates from the NEI:
After clearing heavy explosion debris from tsunami and the various explosions across the site over the last six days, eleven high pressure fire trucks showered unit 3. World Nuclear News understands that 30 tonnes of water "was delivered" in an attempt to shoot water through the holes in the side of the building, which appear to be very close to the fuel ponds themselves...
Despite high levels of radiation close to the units, levels detected at the edge of the power plant site have been steadily decreasing [the below is given in reverse chronological order].
17 March, 4.00pm: 0.64 millisieverts per hour
17 March, 9.00am: 1.47 millisieverts per hour
16 March, 7.00pm: 1.93 millisieverts per hour
16 March, 12.30pm: 3.39 millisieverts per hour
In Japan, engineers have laid a power line that can connect reactor 2 of the Daiichi facility to the off-site power grid, the International Atomic Energy Agency reported. Workers are working to reconnect the power to reactor 2 after they complete spraying water into the reactor 3 complex to provide additional cooling to the used fuel pool. Reconnecting to the power grid is expected to enhance efforts to prevent further damage at the plant.
Japan's Nuclear and Industrial Safety Agency reported on Thursday that the backup diesel generator for reactor 6 is working and supplying electricity to reactors 5 and 6. TEPCO is preparing to add water to the storage pools that house used nuclear fuel rods at those two reactors.
Radiation readings at the Fukushima Daiichi site boundary were measured today at a lower level, between 2 and 3 millirem per hour.
Read more of this post