First concrete for Shin-Kori 4 was poured in August 2009 and the APR-1400 unit is scheduled to begin commercial operation in September 2014. Its schedule is running about one year behind that of Shin-Kori 3, the first APR-1400 to be built. Two more of the 1350 MWe pressurized water reactors are planned for construction at Shin-Ulchin and scheduled to start up in 2016 and 2017. Four have been ordered by Emirates Nuclear Energy Corporation for the Braka plant in the United Arab Emirates to start between 2017 and 2020. The construction and power generation costs of the APR-1400 are reported to be 10% lower than those of OPR-1000 units.