Michele Kearney's Nuclear Wire

Major Energy and Environmental News and Commentary affecting the Nuclear Industry.

Friday, October 31, 2014

NRC Team Ready to Get to Work at Pilgrim Nuclear Power Plant

NRC Team Ready to Get to Work at Pilgrim Nuclear Power Plant

Neil Sheehan
Public Affairs Officer
Region I
 
When the Pilgrim nuclear power plant got a second “white” performance indicator in the same area of performance in 2014 it meant we would ratchet up our level of scrutiny until the underlying issues were resolved.
pilgrimStarting Monday, that scrutiny will take the form of a team inspection at the Plymouth, Mass., facility. Eight NRC inspectors will begin performing evaluations in several key areas.
For one, they will review the evaluation done by Entergy, the plant’s owner and operator, looking at why the problems that triggered the indicator changes occurred. The team will also dig into the fixes, or corrective actions, put in place by the company to prevent the issues from happening again. They will also look at whether the issues could have affected other parts of plant operations. The timeframe for the inspection gave Pilgrim time to evaluate and fix the problems, so the NRC inspectors can make sure the corrective actions are adequate.
Another area the team will assess will be whether there were any safety culture weaknesses that caused or played a part in the performance issues. The NRC defines nuclear safety culture as values and behaviors that emphasize safety over competing goals to ensure protection of people and the environment.
Once the team’s on-site work is finished, the inspectors will brief Entergy at a high level regarding what it has found. That is followed by an inspection report issued within 45 days.
We also plan to conduct a public meeting with Entergy after the inspection is wrapped up. This meeting, which would likely occur in December or January near the plant, will provide a forum for the NRC and the company to discuss the performance issues, their underlying causes and any improvement steps.
The NRC will provide notice on the date, time and location for this session.
As a refresher on earlier developments, the Pilgrim plant’s performance indicator for Unplanned Scrams (shutdowns) with Complications crossed the threshold from “green” to “white” following the third quarter of 2013. Then, in the fourth quarter of last year, the performance indicator for Unplanned Scrams per 7,000 Hours of Operation also changed to “white,” something that occurs if a plant has more than three such shutdowns during the designated period. This placed Pilgrim in the Degraded Cornerstone Column of the Action Matrix used by the NRC to assess plant performance.
And that, in turn, requires the heightened NRC attention to be paid during the team inspection this week.

No comments:

Post a Comment