Cold testing of interim storage facility completed at Ignalina

Cold testing of interim storage facility completed at Ignalina

Cold testing - one of the first stages of the commissioning process - has been completed at the new Interim Spent Fuel Storage Facility (ISFSF) for units 1 and 2 of the shut-down Ignalina nuclear power plant in Lithuania. The work started in January and was completed on 16 June, the plant (SE INPP) announced yesterday.

http://www.world-nuclear-news.org/WR-Cold-testing-of-interim-storage-facility-completed-at-Ignalina-21061601.html