NRC Agrees Modifications to South Carolina Nuclear Plant Adequate If Dam Fails
NRC said the flood
modifications included building new or enhanced flood walls and other
features, as well as moving some power lines and equipment to locations
less prone to flooding. Duke Energy informed the agency two months ago
that those modifications were complete, and a subsequent inspection
caused NRC to determine that the company has satisfied the commitments
in the 2010 confirmatory action letter.
https://ohsonline.com/articles/2016/06/20/nrc-flood.aspx