CNNC Announces Progress At Generation IV Shidao Bay HTR-PM :: The Independent Global Nuclear News Agency

CNNC Announces Progress At Generation IV Shidao Bay HTR-PM :: The Independent Global Nuclear News Agency: The reactor pressure vessel, steam generator and hot gas duct of the second reactor at the Shidao Bay-1 high-temperature gas-cooled reactor-pebble bed module (HTR-PM) demonstration plant under construction in China have been successfully paired and connected, China National Nuclear Corporation said.



The connection for the first of the twin modules was finished on 28 April 2020. The same work had already been finished on 18 March for the second module.



Work on the demonstration HTGR at Shidao Bay in Shandong province, eastern China, began in December 2012.