Monday, December 6, 2010

Iran's key nuclear sites

ran's key nuclear sites

Map of nuclear facilities in Iran

Arak - Heavy water plant

Aerial view of a heavy-water production plant Iran is building a reactor at Arak, where it already has a heavy-water production plant
The existence of a heavy water facility near the town of Arak first emerged with the publication of satellite images by the US-based Institute for Science and International Security in December 2002.
Heavy water is used to moderate the nuclear fission chain reaction either in a certain type of reactor - albeit not the type that Iran is currently building - or produce plutonium for use in a nuclear bomb.
In August 2010, the IAEA visited the IR-40 heavy water reactor site at Arak. It said the facility was still being built but some major equipment had been installed. Iran told the IAEA the operation of the reactor was planned to start in 2013.
The IAEA said that based on satellite imagery, the heavy water production plant appeared to be in operation, but had not had access to it to confirm such reports.

Bushehr - Nuclear power station

Reactor building at the Bushehr nuclear power plant The reactor building at Bushehr was built with Russian help
Iran's nuclear programme began in 1974 with plans to build a nuclear power station at Bushehr with German assistance.
The project was abandoned because of the Islamic revolution five years later, but revived in the 1990s when Tehran signed an agreement with Russia to resume work at the site.
Moscow delayed completion on the project while the UN Security Council debated and then passed resolutions aimed at stopping uranium enrichment in Iran.
In December 2007, Moscow started delivering the canisters of enriched uranium the plant needs.
Earlier in the same month, a US intelligence report said Iran was not currently running a military nuclear programme.
There are two pressurised water reactors at the site.
Satellite images from March 2010 show the first completed reactor building on a site that occupies 2.5 square kilometres (one square mile), about 17 km (11 miles) south of the city of Bushehr. Recent developments include a narrow channel to carry cooling water for the reactor from the Gulf.

Gachin - Uranium mine

Yellowcake Yellowcake is used in the preparation of fuel for nuclear reactors
In December 2010, Iran said it had delivered its first domestically produced uranium ore concentrate, or yellowcake, to a plant that can make it ready for enrichment.
Iran's nuclear chief Ali Akbar Salehi said the first batch of yellowcake had been sent from Gachin mine sent to the Isfahan conversion facility.
Mining operations started at the mine in 2004.
Iran was believed to be running low on its stock of yellowcake, originally imported from South Africa in the 1970s.

Isfahan- Uranium conversion plant

Men work inside of an uranium conversion facility March 30, 2005 Men making hexafluoride gas at the Isfahan uranium conversion facility
Iran is building a plant at a nuclear research facility to convert yellowcake into three forms:
  • Hexafluoride gas - used in gas centrifuges
  • Uranium oxide - used to fuel reactors, albeit not the type Iran is constructing
  • Metal - often used in the cores of nuclear bombs. The IAEA is concerned about the metal's use, as Iran's reactors do not require it as fuel.

Natanz - Uranium enrichment plant

Natanz uranium enrichment plant Iran is planning new facilities at Natanz
Iran resumed uranium enrichment work at Natanz in July 2004, after a halt during negotiations with leading European powers over its programme.
It announced in September 2007 that it had installed 3,000 centrifuges, the machines that do the enrichment. In 2010, Iran told the IAEA Natanz would be the venue for new enrichment facilities - construction of which would start around March 2011.
This is the facility at the heart of Iran's dispute with the United Nations Security Council.
The Council is concerned because the technology used for producing fuel for nuclear power can be used to enrich the uranium to a much higher level to produce a nuclear explosion.

Qom - Uranium enrichment plant

Iranian suspected facility in Qom IAEA says work started on Qom site earlier than Iran suggests
Iran revealed the existence of the Fordo enrichment facility, which is being built about 30km (20 miles) north of Qom, in September 2009.
The facility is believed to be on a mountain on a former Iranian Revolutionary Guards missile site to the north-east of Qom on the Qom-Aliabad highway, Western diplomatic sources say.
Iran said it began the project in 2007 - but the IAEA believes design work started there in 2006.
The IAEA said it expected the Qom site to start enriching uranium in 2011. It is believed to have facility for 3,000 centrifuges for the enrichment of uranium.
Iran wrote to the International Atomic Energy Agency saying it intended to build a plant to enrich uranium to 5% - not enough for a weapon.
http://www.bbc.co.uk/news/world-middle-east-11927720
Enhanced by Zemanta

Sunday, December 5, 2010

US concern as Iran declares nuclear 'self-sufficiency'




Iran produces first uranium yellowcake from southern mineTehran (AFP) Dec 5, 2010 - Iran has produced its first batch of uranium yellowcake, the raw material for enrichment, from a mine in the south of the country, atomic chief Ali Akbar Salehi said on Sunday. "The West had counted on the possibility of us being in trouble over raw material but today we had the first batch of yellowcake from Gachin mine sent to Isfahan (conversion) facility," Salehi said on state television. Conversion is the process by which yellowcake is converted into uranium hexafluoride for enrichment.

The atomic chief said the new step made Iran "self-sufficient" in the entire nuclear fuel cycle as it had previously been obliged to import yellowcake from abroad but he declined to reveal the amount of the first domestically produced batch. "We cannot cover the overall need of the Isfahan facility but we will produce a significant part of it" from the Gachin mine near the Gulf port city of Bandar Abbas, Salehi said. He said Iran would formally notify the International Atomic Energy Agency of its yellowcake production.

The announcement came as Iran is poised to hold a new round of talks with world powers on its controversial nuclear programme in Geneva on Monday. Uranium enrichment lies at the heart of Western concerns about Iran's nuclear activities as the process can produce fuel for nuclear reactors or in highly extended form the fissile core of an atom bomb. Iran denies seeking a weapons capability but has pressed on with uranium enrichment in defiance of repeated UN Security Council ultimatums.
http://www.spacewar.com/reports/US_concern_as_Iran_declares_nuclear_self-sufficiency_999.html Tehran (AFP) Dec 5, 2010 Iran said Sunday it has produced a first batch of uranium yellowcake, the raw material for enrichment, in a move it said "strengthens" its position before talks with world powers on its controversial nuclear programme. In Washington, the White House said the claim raises "additional concerns" but was "not unexpected" since UN sanctions prevent Iran from importing it.
Iranian atomic chief Ali Akbar Salehi said that the Islamic republic was now "self-sufficient" in the entire nuclear fuel cycle.
"The West had counted on the possibility of us being in trouble over raw material but today we had the first batch of yellowcake from Gachin mine sent to Isfahan (conversion) facility," Salehi said on state television.
Conversion is the process by which yellowcake is turned into uranium hexafluoride (UF6) for enrichment.
"This calls into further question Iran's intentions and raises additional concerns at a time when Iran needs to address the concerns of the international community," White House official Mike Hammer said.
Analysts believe Iran has nearly exhausted 600 tonnes of yellowcake acquired from South Africa in the 1970s before the Islamic revolution, triggering speculation that a lack of raw material might halt its nuclear programme.
A February 2009 study by the US-based Institute for Science and International Security (ISIS) said there was scant evidence at the time that Iran had been able to supplement its dwindling yellowcake supply with domestically mined uranium.
Salehi said Iran still cannot meet "the overall need of the Isfahan facility but... will produce a significant part of it" from Gachin near the Gulf port city of Bandar Abbas.
"Iran has become self-sufficient in the entire fuel cycle, starting from (uranium) exploration, mining and then turning it into yellowcake and converting it to UF6 and then turning it into fuel plates or pellets," he said.
He said Iran would formally notify the International Atomic Energy Agency (IAEA) of its yellowcake production, but declined to disclose the amount of the first domestically produced batch.
Enhanced by Zemanta

Sunday, November 28, 2010

US considers military options against Iran




http://www.spacewar.com/reports/US_considers_military_options_against_Iran_999.html Washington (AFP) Nov 28, 2010 Suspicious of Iran's nuclear capacity, the United States is weighing military options in the face of Tehran's announcement it had a nuclear power plant up and running, the top US military officer said Sunday. "We've actually been thinking about military options for a significant period of time," Admiral Mike Mullen, chairman of the US joint chiefs of staff said in an interview with CNN.
Mullen said he doesn't believe that Iran's nuclear plant is for civilian use "for a second."
"In fact, the information and intelligence that I've seen speak very specifically to the contrary. Iran is still very much on a path to be able to develop nuclear weapons, including weaponizing them, putting them on a missile and being able to use them," he said.
Mullen said the United States was focused on dialogue and engagement about Iran's nuclear ambitions, but "in a realistic way."
"They've got a history of gamesmanship that certainly doesn't include closing on significant steps to indicate to the international community that they're not doing this," he said.
On Saturday, Iran said its first atomic power plant built by Russia in Bushehr had begun operations, ahead of a new round of talks with Western powers over the country's controversial nuclear drive.
"Without any propaganda and fuss we sealed the cover of the reactor and all the fuel rods are in the core of the reactor," atomic chief Ali Akbar Salehi was quoted as saying by Fars news agency, without specifying when.
But Salehi said the authorities in the Islamic republic "hope that electricity produced at the Bushehr plant will be connected to the national grid in a month or two."
Iran says it needs the plant, which had been under construction since the 1970s in the southern port city of Bushehr before it was completed by Russia, to meet growing demand for electricity.
But Western governments suspect Iran's nuclear program masks a drive for an atomic weapons capability, an ambition Tehran has steadfastly denied.

Enhanced by Zemanta

Iran says first nuclear plant begins operating




http://www.nuclearpowerdaily.com/reports/Iran_says_first_nuclear_plant_begins_operating_999.html Tehran (AFP) Nov 27, 2010 Iran said Saturday its first atomic power plant built by Russia in Bushehr has begun operations, ahead of a new round of talks with Western powers over the country's controversial nuclear drive. "Without any propaganda and fuss we sealed the cover of the reactor and all the fuel rods are in the core of the reactor," atomic chief Ali Akbar Salehi was quoted as saying by Fars news agency, without specifying when.
But Salehi said the authorities in the Islamic republic "hope that electricity produced at the Bushehr plant will be connected to the national grid in a month or two."
Iran says it needs the plant, which had been under construction since the 1970s in the southern port city of Bushehr before it was completed by Russia, to meet growing demand for electricity.
But Western governments suspect Iran's nuclear programme masks a drive for an atomic weapons capability, an ambition Tehran has steadfastly denied.
Salehi's announcement come ahead of the likely resumption of stalled negotiations between world powers and Iran on Tehran's controversial nuclear programme in Geneva on December 5.
EU foreign policy chief Catherine Ashton said this week she had received "informal confirmations" from Iran about the date and location for the talks, "but I want a formal confirmation."
Iran and six world powers -- the United States, Russia, China, France, Britain and Germany -- have agreed to return to the negotiating table for the first time since October 2009, but two sides diverge on what issues should be on the table.
The world powers want the talks to focus on Iran's uranium enrichment programme but Tehran wants a wider discussion that includes regional security issues.
Iran is under four sets of UN sanctions over its refusal to suspend uranium enrichment, the sensitive process which can be used to make nuclear fuel or, in highly extended form, the fissile core of an atom bomb.
Last month Iran said it has begun loading fuel -- provided by Moscow which also recovers the spent fuel-- into the reactor core of Bushehr plant, a move which brings the facility closer to generating electricity after decades of delay.
Iran had begun transferring the fuel to the facility on August 21, a process which was described as the "physical launch" of the power plant.
On October 4, Salehi said the power plant would be ready to generate electricity by January -- two months later than previously announced.
The process of loading the fuel has suffered some hiccups, which Salehi has previously blamed on "severe hot weather" in Bushehr.
Early October, Salehi said a small leak in a pool beside the Bushehr reactor has delayed the start-up of the nuclear plant and four days ago, he also repeated previous denials by Iranian officials that an extraordinary computer worm, Stuxnet, had in any way harmed Iran's nuclea
Enhanced by Zemanta

Iran: Bushehr Nuclear Reactor Fully Loaded -- Voice of America

Iran: Bushehr Nuclear Reactor Fully Loaded -- Voice of America
http://www.voanews.com/english/news/Iran-Bushehr-Nuclear-Reactor-Fully-Loaded-110905769.html
Iran's nuclear chief says the country's first nuclear reactor is fully loaded and could be operational within months.

Ali Akbar Salehi told state-run television Saturday workers had finished loading fuel rods into the core of the Bushehr nuclear plant, and that it could start generating electricity by February.

Salehi said officials are just waiting for the water in the reactor to heat to the right temperature before moving ahead.

Read more ....

More News On Iran's Nuclear Program

Iran Says Its First Nuclear Power Reactor Will Start Operating by January -- Bloomberg
Iranian nuclear plant nears national electricity production -- CNN
Iran's Bushehr nuclear power plant to join national power grid in two months -- Xinhuanet
Iran says first nuclear plant begins operating -- AFP
Reactor started at Bushehr nuclear power plant -- ITAR-TASS
Iranian Nuclear Plant is Powering Up -- Arutz Sheva
Iran Nuclear Power Plant Completes Fueling -- CRIEnglish
Enhanced by Zemanta

Friday, November 26, 2010

Fuel loading completed at Bushehr


The reactor head of the first reactor at Iran's Bushehr nuclear power plant was successfully installed on 23 November, according to Ali Akbar Salehi, head of the Atomic Energy Organization of Iran (AEOI). This marks the completion of fuel loading, according to a report by the Iranian Students News Agency. Fuel loading activities began on 26 October. Previous reports have indicated that the unit will be grid connected in February 2011. The completion of fuel loading comes alongside continuing concern from the International Atomic Energy Agency (IAEA) about Iran's enrichment activities. An IAEA report dated 23 November concluded, "While the Agency continues to verify the non-diversion of declared nuclear material in Iran, Iran has not provided the necessary cooperation to permit the Agency to confirm that all nuclear material in Iran is in peaceful activities." The report also noted that there was a six-day suspension of uranium enrichment at Iran's Natanz plant, which started on 16 November. Some media sources have linked this to the Stuxnet virus attack, but Iran has officially denied that the virus caused any damage.
Enhanced by Zemanta

Wednesday, November 24, 2010

Iran denies problem with uranium enrichment



Iran's nuclear programme suffered one-day outage: IAEAVienna (AFP) Nov 23, 2010 - Iran's uranium enrichment activities came to a complete halt for at least one day this month, a new restricted UN report revealed Tuesday, amid speculation the activities were the target of a cyberattack. "On November 16, no cascades (of uranium-enriching centrifuges at Iran's Natanz enrichment nuclear plant) were being fed with UF6 (uranium hexaflouride)," the International Atomic Energy Agency wrote in a restricted report, a copy of which was obtained by AFP. During a visit on November 5, IAEA inspectors had verified that more than 4,800 such centrifuges were being fed with nuclear material. And almost the same number were up and running again on November 22. There was no indication yet how long the outage lasted, or whether it was longer than just one day, according to a senior diplomat familiar with the IAEA's investigation. The IAEA report did not contain any explanation about the possible reasons for the outage.

And the diplomat also refused to speculate that it was caused by a computer worm, called Stuxnet, that has infiltrated Iran's nuclear facilities recently. Last week, the computer security firm Symantec said Stuxnet may have been specifically designed to disrupt the motors that power gas centrifuges used to enrich uranium. That has given rise to speculation the worm was intended to sabotage nuclear facilities in Iran, especially the Russian-built atomic power plant in the southern city of Bushehr. The report revealed that Iran has now amassed a stockpile of 3,183 kilogrammes of low-enriched uranium in defiance of orders by the UN Security Council to halt all such activity. Low-enriched uranium or LEU can be used to make nuclear fuel, but can also be refined still further to build an atomic warhead.

The West accuses the Islamic republic of seeking to build a bomb, a claim Tehran vehemently denies. The IAEA has been trying to determine for seven years now the exact nature of Iran's nuclear drive, but has so far been unable to say it is entirely peaceful as Tehran claims. Earlier this year, Iran also began enriching uranium to 20 percent, ostensibly for use as fuel in a research reactor that makes radioisotopes for medical treatment. As a result of its decision to move to higher enrichment, the Security Council slapped a fourth round of sanctions on Iran. According to the new report, Iran has since amassed 33 kilogrammes of 20-percent enriched uranium. IAEA inspectors found that while Iran was feeding nuclear material into more and more uranium-enriching centrifuges at its plant in Natanz, the actual daily rate of production of LEU was not increasing significantly. That also could be an indication of possible technical problems, experts say.
http://www.spacewar.com/reports/Iran_denies_problem_with_uranium_enrichment_999.html Tehran (AFP) Nov 23, 2010 Iran denied on Tuesday claims that its sensitive uranium enrichment work has been hit by technical problems and said its nuclear programme has not been harmed by the Stuxnet computer worm. Atomic chief Ali Akbar Salehi also rejected allegations by Western powers that Iran lacks the know-how to make nuclear fuel plates and was adamant it would be producing fuel for a research reactor by September 2011.
And he welcomed the International Atomic Energy Agency's latest report on Iran, saying his country had "cooperated" with the UN nuclear watchdog.
An IAEA report obtained by AFP on Tuesday said that "on November 16, no cascades (of uranium-enriching centrifuges at Iran's Natanz enrichment nuclear plant) were being fed with UF6 (uranium hexaflouride)."
There was no indication yet how long the outage lasted, according to a senior diplomat familiar with the IAEA's investigation.
The report did not say what the reasons for the outage might have been.
And the diplomat refused to speculate that it was caused by a computer worm, called Stuxnet, that has infiltrated Iran's nuclear facilities recently.
Computer security firm Symantec said last week that Stuxnet might have been designed to disrupt the motors that power gas centrifuges used to enrich uranium.
That has given rise to speculation the worm was intended to sabotage nuclear facilities in Iran, especially the Russian-built atomic power plant in the city of Bushehr.
Salehi "denied (media) reports and what has appeared in the IAEA report about a one-day halt of enrichment activities in Natanz," the ISNA news agency said.
"In an enrichment plant centrifuges are always being installed, operated, repaired and replaced and this is natural," he said.
He made a similar denial earlier in the day before the IAEA report was made public.
He appeared to be reacting to comments by Olli Heinonen, former IAEA deputy director, who said on Monday that technical problems were slowing down Iran's uranium enrichment.
Centrifuges for enrichment were operating at only 60 percent of capacity and Iran for some reason has removed hundreds of the machines, he said, and "this indicates there is a problem."
In February, Iran started refining uranium to 20 percent purity after a deadlock over a nuclear fuel swap deal drafted by the IAEA and aimed at providing fuel for the Tehran medical research reactor.
Salehi said on Tuesday the enrichment process was continuing apace.
"By the month of Shahrivar next year (September 2011), we will produce fuel for the reactor," he was quoted as saying by IRNA.
He also repeated denials by Iran that Stuxnet had harmed its nuclear programme.
"This virus bumped into a dead-end, a wall, and the enemies could not achieve the goals they had hoped for in the past one and a half years," he said.
Iran has been slapped with four sets of UN Security Council sanctions over its refusal to suspend enrichment.
Enriched uranium can be used as fuel to power nuclear reactors as well as to make the fissile core of an atom bomb. Tehran has repeatedly denied Western accusations that it is working to produce a nuclear bomb.
The IAEA report revealed that Iran has now amassed a stockpile of 3,183 kilogrammes (7,003 pounds) of low-enriched uranium and 33 kilos of 20 percent enriched uranium.
Stalled negotiations between world powers and Iran over Tehran's nuclear programme are now likely to resume on December 5 in Geneva, according to top European Union diplomat Catherine Ashton, for the first time since October 2009.
Referring to the IAEA report, Salehi said it had "improved in comparison with the past and we regard this as a good sign. However, the content is similar to those before."
"There might be different interpretations of cooperation, but Iran will continue to cooperate with the agency within the safeguard agreement and there is no reason to cooperate beyond that," he added.
The report complained that little had changed by way of the IAEA's overall investigation.
It also said Iran was refusing to halt enrichment and to answer questions that the nuclear watchdog has had for the past two years about a possible military dimension to its nuclear work.
The nine-page document has been circulated to IAEA member states and will be discussed by the agency's 35-member board of governors at the beginning of December.
Enhanced by Zemanta

Tuesday, November 2, 2010

TVEL signs package of Chinese fuel contracts

TVEL signs package of Chinese fuel contractshttp://www.world-nuclear-news.org/ENF-TVEL_signs_package_of_Chinese_fuel_contracts-0211108.html

Signing ceremony (Image: TVEL)Russian nuclear fuel company TVEL has signed a package of contracts which will see it supply nuclear fuel, fuel production technology and zirconium fuel components to China. The contracts relate to the Tianwan nuclear power plant.
Enhanced by Zemanta

Friday, October 29, 2010

Russia joins list of countries keen to supply nuclear plants to SA

Russia’s State atomic energy corporation, Rosatom, is providing South Africa’s Department of Energy with briefings on the latest generation of Russian nuclear power plants. The first such briefing took place in August, in Moscow, and the second should occur in Pretoria, probably before the end of this year.
The intention is that the second briefing will take place after the finalisation of South Africa’s Integrated Resource Plan 2010 (IRP 2010), which was issued in draft form earlier this month. Although the period for comment on the IRP2010 is likely to be extended, government still wants it to be finalised before the end of the year.
The IRP2010 identifies the country’s power generation options for the next 20 years. One of these is nuclear, and Russia wants to be one of the bidders for South Africa’s next nuclear power plant.
The Russian nuclear industry learned a great deal from the Chernobyl catastrophe in the Ukraine in the then Soviet Union, in 1986. As a result, modern Russian nuclear power reactors have multiple protection systems.
Since then, the Russians have focused their attention, like France and the US, on pressurised water reactors (PWRs) – abbreviated as VVER in Russian. According to the US Energy Information Administration, an American government agency, today’s VVER designs “conform to international standards”.
Russia is offering South Africa the latest generation of its VVER-1000 reactor in the AES-91/99 nuclear power plant design. (The Russians have separate designations for reactors and for the nuclear power plants). In 2003, the AES-91/99 design (including the reactor) was certified as complying with European Union standards by Finnish experts. The AES-91/99 uses the latest version – V-466 – of the VVER-1000 reactor (VVER-1000/466 for short). But other options are available. More at:


http://www.pimagazine-asia.com/index.php?page=shownews&news=2828
Enhanced by Zemanta

Tuesday, October 26, 2010

Argentina to join small group of uranium-enriching countries

CIVIL NUCLEAR
http://www.nuclearpowerdaily.com/reports/Argentina_to_join_small_group_of_uranium-enriching_countries_999.html


Buenos Aires (AFP) Oct 25, 2010 Argentina's President Cristina Kirchner Monday rededicated a uranium enrichment plant in southern province of Rio Negro, saying that next year Argentina would join the group of 10 countries producing the fuel for peaceful use. "In November 11, a first sample of enriched uranium will be obtained, at which point, Argentina will join the group of 10 countries producing enriched uranium" for peaceful ends, Kirchner said.
The same plant was used to produce enriched uranium from 1982 to 1983 but then closed because of lower international prices, the Chernobyl nuclear disaster in 1986 and unfavorable public opinion, officials said.
Enhanced by Zemanta

Friday, October 22, 2010

Iran admits some of its nuclear scientists spied for the West

A top-level Iranian government official has admitted that some scientists and technicians in Iran’s nuclear energy program were successfully lured into spying for Israeli and Western intelligence agencies in the past. The disclosure, which was characterized as “stunning” by the Associated Press, marked the first-ever open admission by the Iranian government that the country’s nuclear energy program has been penetrated by foreign spies. It was made last weekend by Ali Akbar Salehi, Iran’s Vice President and Director of the country’s Atomic Energy Organization. According to the Iranian government-controlled Fars News Agency, Vice President Salehi told an audience that individual scientists and technicians working in Iran’s nuclear program had used their access to classified relevant information to benefit from “foreign purchases and commercial affairs”. The Fars report was vague and made no specific reference to the nature of the compromised information or the precise timing of the alleged espionage. But it did note that Mr. Salehi made clear that, although “[i]n the past personnel had easy access to information”, this “is not the case anymore now”. More at:
http://intelligencenews.wordpress.com/2010/10/22/01-580/
Enhanced by Zemanta

Thursday, October 21, 2010

IAEA Wants Research Reactors to use Low Enriched Uranium

 There are approximately 250 operating civilian research and test reactors worldwide, of which around 75 use highly enriched uranium (HEU) as their fuel. But the use of HEU has the potential of nuclear proliferation as it could also be used for producing material used for nuclear weapons. The IAEA works with global partners focusing on how to convert HEU reactors to ones that can use low enriched uranium (LEU). More at:
http://nuclearstreet.com/nuclear_power_industry_news/b/nuclear_power_news/archive/2010/10/21/IAEA-Wants-Research-Reactors-to-use-Low-Enriched-Uranium-102102.aspx
Enhanced by Zemanta

Iran Claims To Have Produced 30 Kilograms Of Enriched Uranium

(RTTNews) - Iran, slammed with a fifth round of UN sanctions for not stopping uranium enrichment, has already produced 30 kilograms of the potential nuclear-bomb-making material, according to the nation's atomic chief.http://www.rttnews.com/Content/MarketSensitiveNews.aspx?Id=1450741&SM=1
Enhanced by Zemanta

Wednesday, October 20, 2010

Iran has 30 kg of high level uranium: atomic chief

ran said on Wednesday it has produced around 30 kilogrammes of 20 percent-enriched uranium, in defiance of UN sanctions imposed on Tehran to suspend the contentious nuclear work. "We have produced nearly 30 kilogrammes (66 pounds) of 20 percent enriched uranium so far," Iran's atomic chief Ali Akbar Salehi was quoted as saying by ISNA news agency.
World powers led by Washington want Tehran to suspend its uranium enrichment activity, which is at the centre of fears that Iran is developing a nuclear weapons.
Enriched uranium can be used as fuel to power nuclear reactors as well as to make the fissile core of an atom bomb.
World powers backed new UN sanctions against Iran on June 9 after they were infuriated by Tehran's decision to enrich uranium to 20 percent, which theoretically brings it closer to the 90 percent purity used to make a nuclear weapon. Iran denies its atomic programme is aimed at making weapons.
President Mahmoud Ahmadinejad ordered Iran's atomic body in February to start refining uranium to 20 percent after a nuclear fuel swap deal drafted by the UN atomic watchdog and aimed at providing fuel for a Tehran research reactor hit a deadlock.
Iran claims that by September 2011 it will domestically produce the required fuel and the actual fuel plates to power the reactor.
Western powers say that the Islamic republic does not possess the technology to make the plates.
Meanwhile, Iran and the group of six world powers -- Britain, China, France, Germany, Russia and the United States -- are to hold talks on Tehran's overall nuclear programme in mid-November.

Enhanced by Zemanta

Sunday, October 17, 2010

One month delay in launching Bushehr power plant: nuclear official

October 17, 2010 Tehran Times Political Desk TEHRAN – The launch of Bushehr nuclear power plant is delayed one month due to some minor technical problems, Atomic Energy Organization of Iran Deputy Director Mohammad Ahmadian has said. “After inspection, we made sure that we are not faced with any serious problem, but there are some minor problems including a small leak in a pool in the middle of the reactor which was fixed,”
 
Ahmadian told IRNA in an interview published on Saturday.“It takes one month to fix these minor problems, so unfortunately there will be one month delay in the transfer of fuel rods into the reactor core,” he added
 
.On September 11, Iran’s Nuclear Chief Ali Akbar Salehi announced that nuclear fuel will be loaded into the core of the Bushehr reactor at the beginning of the Iranian calendar month of Mehr (September 23 to October 22), and afterwards, the Bushehr nuclear power plant will begin operation
 
.Salehi also said the nuclear plant will be able to produce electricity in the Iranian calendar month of Azar (November 22 to December 21).The plant, located near the port of Bushehr on the coast of the Persian Gulf, will produce 1000 megawatts of electricity once all the fuel rods are loaded into the core of the reactor
 
.The Bushehr reactor may save Iran 11 million barrels of crude oil or 1.8 billion cubic meters of gas per year, the London-based World Nuclear Association has estimated.The plant will also put Iran at least a decade ahead of more prosperous Middle Eastern neighbors such as the United Arab Emirates, which plans to build four nuclear plants by 2020.